LHC Restart at 3.5 TeV: CERN Prepares for 2009-2010 Run

  • Thread starter Vanadium 50
  • Start date
  • Tags
    Lhc
In summary: July 2, causing significant power outages and bringing the machine to a temporary standstill. By 7:00 p.m. on July 3, the storm had passed, but the repairs continued into the early hours of July 4. More than 2000 volts of electricity were required to get the machine restarted, and the start-up was finally achieved at 3:37 p.m. on Sunday, July 3. The Tevatron has reached its goal of accelerating protons to 500 GeV. This record was set at 3:37 p.m., Sunday, July 3. After a two-day delay due to repairs, the machine was finally able to accelerate protons
  • #1
Vanadium 50
Staff Emeritus
Science Advisor
Education Advisor
2023 Award
33,247
19,746
The following is on CERN's website:

Rolf Hauer" said:
The LHC will run for the first part of the 2009-2010 run at 3.5 TeV per beam, with the energy rising later in the run. That's the conclusion that we've just arrived at in a meeting involving the experiments, the machine people and the CERN management. We've selected 3.5 TeV because it allows the LHC operators to gain experience of running the machine safely while opening up a new discovery region for the experiments.

The developments that have allowed us to get to this point are good progress in repairing the damage in sector 3-4 and the related consolidation work, and the conclusion of testing on the 10000 high-current electrical connections last week. With that milestone, every one of the connections has been tested and we now know exactly where we stand.

The latest tests looked at the resistance of the copper stabilizer that surrounds the superconducting cable and carries current away in case of a quench. Many copper splices showing anomalously high resistance have been repaired already, and the tests on the final two sectors revealed no more outliers. That means that no more repairs are necessary for safe running this year and next.

The procedure for the 2009 start-up will be to inject and capture beams in each direction, take collision data for a few shifts at the injection energy, and then commission the ramp to higher energy. The first high-energy data should be collected a few weeks after the first beam of 2009 is injected. The LHC will run at 3.5 TeV per beam until a significant data sample has been collected and the operations team has gained experience in running the machine. Thereafter, with the benefit of that experience, we'll take the energy up towards 5 TeV per beam. At the end of 2010, we'll run the LHC with lead-ions for the first time. After that, the LHC will shut down and we'll get to work on moving the machine towards 7 TeV per beam.
 
Physics news on Phys.org
  • #2
So on schedule for full power in December 2012 then ? (sorry)
 
  • #3
Isn't that topic that earns an automatic thread lock?

Anyway, as they say, "It's not the end of the world if it runs at lower energy".
 
  • #4
Its definitely dissappointing, we've been hearing rumors about the lower power output for awhile now and its screwing up scheduling.

What seems worse to me, is that there are still some structural problems within the LHC that could cause further quenches, the 7 TEV number while conservative is also influenced by politics and the possibility for further catastrophes is not remote.
 
  • #5
It's also a slight amount of PR spin.
It's not just achieving a particular energy that is the goal - it's getting a decent intensity at that energy that really takes the work.
Even if everything had worked on day 1 it was still going to take years of tweaks to get to full beam power at 7Tev
 
  • #6
The Fermilab Tevatron first tried accelerating beam on the morning of July 3, 1983. By 6:00 PM that afternoon, they had reached 512 GeV. The next several months were used to trim up the machine, increase the current, and reach over 900 GeV. One advantage Fermilab had is that their ring is only 6.28 Km in diameter, compared to 27 Km for LHC. Another is that it was designed to ramp from injection energy to full energy in 20 seconds, and cycle once a minute, so it was an easy machine to tune.

(From Fermilab weekly newspaper)
[TEVATRON] REACHES GOAL, SETS ENERGY RECORD!

by Thornton Murphy

The [Tevatron] has reached its primary design goal: accelerating protons to 500 GeV in a ring of superconducting magnets. In fact, the energy was 512 GeV--a new world record for accelerators. The record was set at 3:37 p.m., Sunday, July 3, only 13 hours after the first serious attempt to accelerate beam above the injection energy of 150 GeV.

News of this historic achievement spread rapidly-by telephone and telex to all quarters of the world. The Control Room rapidly filled with off-shift workers and other well-wishers as the champagne was broken out.

The events leading up to this milestone followed the usual pattern of a long pause while a blockade to progress was diagnosed, followed by sudden leaps forward. Difficulties in achieving coasting beam at 150 GeV, reported two weeks ago, were finally tracked to a misdesigned flange in the C0 straight section and a Kimwipe left in the bore tube in A0. After the Kimwipe was removed on June 25, coasting beam was rapidly achieved. The rf cavities were proven capable of maintaining the bunching at 150 GeV and even accelerated the beam slightly.

There followed a two-day down period for necessary repairs with the expectation that acceleration towards 500 GeV would begin soon after startup on June 30. Unfortunately, the weather did not cooperate. A lightning bolt struck service building E0 at 3 a.m. on Friday, July 1, damaging enough sensitive electronics to cause six hours of diagnosis and repairs, followed immediately by more lightning-induced trips around 9:30 a.m. The next night torrential rains found their way all the way to electronics racks.

When all was finally ready to attempt acceleration, beam reached the top of the 250 GeV ramp on the very first pulse at 3:12 a.m., Sunday, July 3. After a shift of studies at that energy, the current ramp in the magnets was reset to 400 GeV and beam accelerated to that energy at 1:38 p.m. A "go for the record" spirit then prevailed; after readjusting the ramp again, the energy goal was exceeded amidst jubilation at 3:37 p.m.
 
  • #7
... and the Tevatron took a long time to deliver significant luminosity as they had large problems with anti-proton production, containment and cooling. At least at the LHC we don't need fancy anti-protons.
 
  • #8
This thread is not meant to be used as another "doomsday" thread. Those have been sufficiently addressed in many previous threads in this forum. There has been nothing new, and so, no new discussion on that topic is allowed in this one.

Zz.
 
  • #9
lightning?

Bob S said:
(From Fermilab weekly newspaper)
[TEVATRON] REACHES GOAL, SETS ENERGY RECORD!

by Thornton Murphy

… A lightning bolt struck service building E0 at 3 a.m. on Friday, July 1, damaging enough sensitive electronics to cause six hours of diagnosis and repairs, followed immediately by more lightning-induced trips around 9:30 a.m. The next night torrential rains found their way all the way to electronics racks.

I didn't realize the Tevatron had been affected by lightning (in the service building).

Are all the LHC's service facilities well underground, away from lightning?
 
  • #10


tiny-tim said:
Are all the LHC's service facilities well underground, away from lightning?
The beam and the detectors are well underground, there is still a lot of buildings and equipement on the surface. Switzerland doesn't suffer from lightning to the same extent as the midwest.
I think the main complaint from high energy colleagues (that is people who work in high energy physics - not just those that drink too much coffee) is that every time there is a warm spell the AC fails and all the computers get shut down

Traditionally CERN doesn't run in the winter to reduce the power usage in the area.
 
Last edited:
  • #11


So the LHC will work perfectly :approve: … except in the winter and the warm weather? o:)
 

1. What is the LHC and why is it important?

The LHC, or Large Hadron Collider, is the world's largest and most powerful particle accelerator. It is located at the European Organization for Nuclear Research (CERN) in Switzerland and is used to study the fundamental properties of matter and the origins of the universe. It is important because it allows scientists to recreate conditions similar to those just after the Big Bang, giving us a better understanding of the fundamental building blocks of our universe.

2. Why is the LHC restarting at 3.5 TeV?

The LHC was initially designed to operate at an energy of 7 TeV, but in 2008 a fault in the electrical connections caused an incident that delayed the start-up. To ensure the safety of the accelerator and the experiments, it was decided to restart the LHC at half of its intended energy (3.5 TeV) for the first run. This lower energy allowed for thorough testing and improvements to be made before ramping up to the full energy.

3. What are the goals of the 2009-2010 run at the LHC?

The main goal of the 2009-2010 run is to collect data at 3.5 TeV and perform comprehensive tests of the accelerator and its systems. This will allow scientists to fine-tune the LHC and prepare for higher energy collisions in future runs. Additionally, the LHC will also be used to search for new particles, such as the elusive Higgs boson, and to study the properties of known particles in more detail.

4. How long will the LHC run at 3.5 TeV?

The LHC is expected to run at 3.5 TeV for approximately 18-24 months. After this first run, the energy will be increased to 7 TeV for another period of data collection and experiments. This cycle of running and upgrades will continue for many years, allowing for new discoveries and advancements in particle physics.

5. What safety measures are in place for the LHC?

CERN has implemented numerous safety measures to ensure the safe operation of the LHC. These include strict protocols for handling and testing of equipment, as well as multiple redundant safety systems and emergency shutdown procedures. Additionally, an international team of experts continuously monitors the operation of the LHC and conducts regular safety assessments. The LHC has been deemed safe by these experts and there is no evidence to suggest that it poses any threat to the public or the environment.

Similar threads

  • High Energy, Nuclear, Particle Physics
Replies
1
Views
1K
  • High Energy, Nuclear, Particle Physics
Replies
20
Views
2K
  • High Energy, Nuclear, Particle Physics
Replies
1
Views
841
  • High Energy, Nuclear, Particle Physics
2
Replies
57
Views
13K
  • High Energy, Nuclear, Particle Physics
Replies
30
Views
2K
  • High Energy, Nuclear, Particle Physics
4
Replies
109
Views
16K
  • High Energy, Nuclear, Particle Physics
Replies
1
Views
2K
  • High Energy, Nuclear, Particle Physics
2
Replies
69
Views
12K
  • Sticky
  • High Energy, Nuclear, Particle Physics
Replies
28
Views
7K
  • Beyond the Standard Models
Replies
1
Views
2K
Back
Top