Creating a nuclear power plant

In summary: Senior Vice President for Nuclear Development at Westinghouse comments on how long it takes to build a nuclear power plant. Westinghouse estimates that it takes around four to five years to build a new nuclear power plant, with the final approval coming in around 2002. The last reactor to come online in the United States took 25 years to build, and a period of 36 months is quite optimistic. Probably 4-5 years is more realistic, and perhaps 6 years is even more so. One problem will be getting the piping and pressure vessels/steam generators, which are typically fabricated outside of the United States. Any plant will be new, and even though the Nuclear Regulatory Commission has adopted a simplified licensing process, the utility will probably be cautious.
  • #1
Pengwuino
Gold Member
5,124
20
How long does it take for a nuclear power plant to be built and to have its first reactor come on line? Let's start the time line at basically when the permit is requested and end it when the first reactor goes fully online. What kind of time period are we looking at there in the best case scenarios with no massive interuptions or complications occurring?
 
Engineering news on Phys.org
  • #2
Pengwuino said:
How long does it take for a nuclear power plant to be built and to have its first reactor come on line?
There are claims of 36 months for the new Westinghouse AP600/AP1000. The last reactor unit to come online in the United States took 25 years to build.
 
  • #3
Well I wouldn't suppose that all nuclear power plants take 25 years to make just as I wouldn't suppose a claim would be very accurate as to the average time it woudl normally take.
 
  • #4
http://www.tvo.fi/486.htm

We should've our latest up 2009, the final ok for building came around mid 2002. It's a third unit for this plant, but basically they're building it as a separate one.
 
Last edited by a moderator:
  • #5
36 months may be optimistic, but it is believable from the point of starting construction to going critical. The reason a lot of plants took a long time was due to weaknesses in the licensing process allowing for interruptions and delays at many junctures. This increases construction time and drives up costs substantially.

New regulatory procedures are in place to hopefully reduce this occurrence. For instance, the reactor design is licensed separately and before the plant is built, and there are set time periods for public debate.
 
  • #6
hitssquad said:
There are claims of 36 months for the new Westinghouse AP600/AP1000. The last reactor unit to come online in the United States took 25 years to build.
A period of 36 months is quite optimistic. Probably 4-5 years is more realistic, and perhaps 6 years is even more so.

One problem will be getting the piping and pressure vessels/steam generators. At the present time, these components are fabricated outside the US.

Any plant will be new, and even though the NRC has adopted a simplified licensing process, the utility will probably be cautious.

As for 25 years, I suspect that is a reference to Watts Bar, and this is due to extraordinary circumstances at TVA. They were overextended with multiple plants (including the unfinished Bellefonte units - first B&W plants along RWE's Mulheim-Kaerlich designed to use 17x17 fuel). The management put all the resources into upgrading and restarting Browns Ferry 2 & 3, with BF1 still mothballed. Bellefonte units are history. :frown:
 
  • #7
BCRion said:
36 months may be optimistic, but it is believable from the point of starting construction to going critical. The reason a lot of plants took a long time was due to weaknesses in the licensing process allowing for interruptions and delays at many junctures. This increases construction time and drives up costs substantially.

New regulatory procedures are in place to hopefully reduce this occurrence. For instance, the reactor design is licensed separately and before the plant is built, and there are set time periods for public debate.

Let me just elaborate some on what BCRion has said.

The licensing process in the USA is a two step process. First the utility applies to build
the plant; an action that can be, and frequently is; challenged in court. After a protracted
period of lawsuits and public comment - the construction permit is granted and the utility
can build the plant. After the plant is constructed, the utility has to apply for an
operating license; and the whole process - lawsuits and all, questioning whether the plant
should even exist; starts all over again.

Can you imagine building your home in such circumstances? You convince all the zoning
boards and planning boards that your house will be acceptable to the community and
obtain your building permit. Then after properly construnction the house as per the permit,
and as verified by the building inspector; you would then have to apply for a permit to
actually inhabit the house. During this second permitting process; anybody can challenge
any of the features and siting of the now completed house.

That's the way nuclear power used to be licensed in the USA. The Congress has done
some reform of the laws. Hopefully they have instituted a sensible process for licensing
new reactors.

Dr. Gregory Greenman
Physicist
 

1. What is a nuclear power plant?

A nuclear power plant is a facility that uses nuclear reactions to generate electricity. It works by using a nuclear reactor to heat water and produce steam, which then drives a turbine to generate electricity.

2. Why is nuclear energy used in power plants?

Nuclear energy is used in power plants because it is a reliable, efficient, and low-carbon source of electricity. It also produces large amounts of energy, making it a cost-effective option for meeting the increasing demand for electricity.

3. How is nuclear waste managed in a nuclear power plant?

Nuclear waste is managed through a process called nuclear fuel cycle. This involves storing the waste in specially designed containers and eventually disposing of it in a secure underground repository. Some waste can also be reprocessed and used as fuel in other reactors.

4. What are the safety measures in place for nuclear power plants?

Nuclear power plants have multiple safety measures in place to prevent accidents and protect the environment and public health. These include redundant safety systems, regular inspections and maintenance, and emergency response plans.

5. How long does it take to build a nuclear power plant?

The time it takes to build a nuclear power plant can vary depending on the design and location. On average, it takes about 5-7 years to build a new nuclear power plant. However, the process can take longer due to regulatory approvals, public hearings, and other factors.

Similar threads

  • Nuclear Engineering
2
Replies
41
Views
3K
Replies
20
Views
2K
Replies
5
Views
4K
Replies
25
Views
4K
Replies
52
Views
7K
  • Nuclear Engineering
Replies
4
Views
2K
Replies
6
Views
17K
  • Nuclear Engineering
Replies
13
Views
2K
  • Nuclear Engineering
Replies
5
Views
5K
  • Nuclear Engineering
Replies
4
Views
6K
Back
Top