| New Reply |
Long Beam Span |
Share Thread | Thread Tools |
| Jul2-12, 07:41 PM | #1 |
|
|
Long Beam Span
Are there any structural engineers here or know the stuff. I'd like to know this.
Can structural engineers design long span beam for example 12 meters reinforced concrete beam that is as good as standard 6 meter beam in seismic performance or are 6 meter beams always better compared to 12 meters beam even if the latter were designed for ultimate seismic performance? |
| Jul3-12, 03:49 AM | #2 |
|
|
For vibration analysis you have to consider the whole structure (including the foundations), not just the individual components separately since the connections play a great part in the result.
So it depends what your 6m and 12m beams are connected to and how they are connected. |
| Jul3-12, 06:38 PM | #3 |
|
|
|
| Jul4-12, 02:15 AM | #4 |
|
|
Long Beam Span
Vibration is just the more general term as there are other sources of excitation besides seismic activity.
For example the beams of motorway bridges are subject to continual vibration and are quite a bit longer than 12m. That is less important what is important is the connection conditions of your beams. Another important factor is the natural frequency of vibration. |
| Jul4-12, 12:25 PM | #5 |
|
|
|
| Jul4-12, 12:47 PM | #6 |
|
|
Two 6m span beams would require a centre support that is not present with a 12m one so would add to the cost.
You have been asking about reinforced concrete. This is usually priced at a rate per cu metre placed so the cost would likely be the same for the beams either way. I don't see that any heavier duty craneage would be required 12m is not such a significant increase in size. |
| Jul4-12, 06:29 PM | #7 |
|
|
|
| Jul4-12, 07:00 PM | #8 |
|
|
Most building component sizes are decided by architectural considerations not structural ones. If a longer span beam is specified by the architect then the structural engineer will design a suitably stronger one.
Beams of 6m span are probably so lightly loaded that they are only just above what we call 'minimum steel'. That is the steel required to control cracking. It is unusual to use RC beams in the UK in any case, steel is more normal. Suspended floors are normally RC slabs or prestressed. |
| Jul5-12, 05:31 AM | #9 |
|
|
|
| Jul5-12, 09:10 AM | #10 |
|
|
I said that under standard building contracts reinforced concrete is priced at a rate per cu metre placed. That is the UK standards method of measurement. Civil engineering contracts are priced differently so the reinforcement, concrete and formwork are all measured separately. It is actually unlikely that there would be a greater number of reinforcing bars in the longer beam. Just that they would be larger diameter. |
| Jul5-12, 12:02 PM | #11 |
|
|
Note I'm not constructing any of this, of course but just want to understand the design of certain office near mine. Thanks. |
| Jul5-12, 04:26 PM | #12 |
|
|
Do you mean something like this?
So the upper floor is divided into 4 slabs 6m x 6.5m. |
| Jul5-12, 06:02 PM | #13 |
|
|
Yes. But with the difference there are two 12-meter beams in the middle between the front and back making up 4 side to side beams (not 3 as your drawing shows). Also the girder is not steel i-beam but RC beam and it has same level as the side to side RC beam.. meaning it is embedded like in normal column-beam joint so the definition of girder as something supporting smaller beams don't hold. I wonder if you also defined a girder as something just to support slabs and not exactly the beams (wherein the 12 meter RC beam can stand on their own). |
| Jul6-12, 02:41 AM | #14 |
|
|
OK I think I understand.
There are 3 columns at the front, 3 at the back, and 4 down each side, making 10 in all. avoiding counting corners double). They are presumably evenly spaced. They are connected by a system of rc beams at the top. This network of beams divides the support for the upper floor into 3 strips 4.3m x 12m. When complete this makes an rc frame. I would guess that the upper floor might be then constructed by lifting precast beams or floor units to span 4.3m onto the frame and screeding over the top. That would avoid slab formwork and 4 - 5 m precast beams are not that large and readily handleable by a small crane or even a digger arm. If the floor units can be cast off site or on site whilst the rc frame is being constructed there will not be some weeks waiting time for the floor concrete to cure. |
| Jul6-12, 05:15 AM | #15 |
|
|
|
| Jul6-12, 06:50 AM | #16 |
|
|
Rough guess
75 to 100mm concrete slab 240 kg per sq metre = 180*12*13 to 240*156 = 25tonne to 35 tonne metal sheet roof 6 - 10 kg /sqm plus 4 trusses at 750kg each = 3 to 5 tonnes |
| Jul6-12, 07:10 AM | #17 |
|
|
|
| New Reply |
| Thread Tools | |
Similar Threads for: Long Beam Span
|
||||
| Thread | Forum | Replies | ||
| Finding the B field in a long cylindrical hole in a long wire | Classical Physics | 1 | ||
| structural engineering - sizing a beam using loads/span | Engineering, Comp Sci, & Technology Homework | 2 | ||
| span(S1 ∩ S2) ⊆ span(S1) ∩ span(S2) | Linear & Abstract Algebra | 1 | ||
| How long can you maintain your concentration span? | General Discussion | 18 | ||
| Prove span(S1 U S2) = span(S1) + span(S2) | Calculus & Beyond Homework | 10 | ||