Can someone explain to me the basic process involved in an approach to critical with a nuclear reactor. I understand that you basically start with the rods all the way in and bring them out, while taking counts - waiting for them to stabilize. I understand with the penultimate method, you change the control rod position and take count rates, and then take the ratio of the count rates and extrapolate to the x-axis with each measurement in order to determine the critical point, however I'm confused as to how the 1/M method works to find the critical position.

Thanks,
Derek
Phys.Org News Partner Science news on Phys.org
Scientists discover RNA modifications in some unexpected places
Scientists discover tropical tree microbiome in Panama
'Squid skin' metamaterials project yields vivid color display
jim hardy
#2
Feb21-13, 12:24 PM
Sci Advisor
PF Gold
jim hardy's Avatar
P: 3,739
...however I'm confused as to how the 1/M method works to find the critical position.
I likely don't understand the question:

It's a beautifully simple graphical method.

Plot rod position (or dilution) on Ordinate
1/m on Abscissa

Since multiplication is approaching infinity as you approach criticality,
1/m is approaching zero - but you don't multi-decade log graph paper to see it.

Extrapolate your slope to intersect ordinate and you have an estimate. Closer you get, the better your estimate.

After you do one it's second nature.


Probably i answered the wrong question, though.


Register to reply

Related Discussions
Which approach is nicer? UK MEI approach? American approach? Academic Guidance 0
Volume, washer method another approach Calculus 0
Physics summer placements for penultimate year undergrad? Career Guidance 0
Sub Critical, critical and supercritical - Question High Energy, Nuclear, Particle Physics 0