- #1
- 4
- 0
Hello All,
I have a question for which I'd like an authoritative answer, if some physics genius would be so kind. I'll try to provide as much background as I can but follow up questions for clarity are more than welcome!
So I'm working on the design for a patent application and it involves a series of custom aluminum square tubing pieces held together with either standard 5/8" hitch pins or any 5/8" in bolt. The drawing speaks volumes if you would like to refer to it as you read. Here are the particulars:
Piece A
The problem...because these pieces are meant to attach to each other one after the other (up to 6 or 7 in a row), and there is a 1/16" gap between each connection, the entire system sags about 5 or 6" on the end. This is not surprising, and the obvious answer long-term is to do one of the following:
If I raise the holes off the center-line will it reduce the "slack" anymore than leaving them on center-line? For example, if all holes were moved vertically 1/8" of an inch, would there be less slack than where they are now? To make it relevant to physics...if there is a downward force on piece A, would the force on the pins be different if they were moved vertically 1/8" above center?
Any help you could provide would be helpful!
Thanks,
Matt
I have a question for which I'd like an authoritative answer, if some physics genius would be so kind. I'll try to provide as much background as I can but follow up questions for clarity are more than welcome!
So I'm working on the design for a patent application and it involves a series of custom aluminum square tubing pieces held together with either standard 5/8" hitch pins or any 5/8" in bolt. The drawing speaks volumes if you would like to refer to it as you read. Here are the particulars:
Piece A
- 2" square aluminum tubing (this dimension cannot change)
- About 18" long
- 5/8" D holes placed about 3" apart
- 2.5" square aluminum tubing
- 3/16" thick wall
- Holes close to the edge are 2" from the edge and the inside holes are 3" from the outside holes
The problem...because these pieces are meant to attach to each other one after the other (up to 6 or 7 in a row), and there is a 1/16" gap between each connection, the entire system sags about 5 or 6" on the end. This is not surprising, and the obvious answer long-term is to do one of the following:
- Reduce the gap (which means increasing the thickness of the wall of piece B)
- Add a second hole (done...originally these pieces had only one hold and one hitch pin holding them together)
- Reduce the engineering tolerance for the hole(s)
- Add some sort of shim at each connection point.
If I raise the holes off the center-line will it reduce the "slack" anymore than leaving them on center-line? For example, if all holes were moved vertically 1/8" of an inch, would there be less slack than where they are now? To make it relevant to physics...if there is a downward force on piece A, would the force on the pins be different if they were moved vertically 1/8" above center?
Any help you could provide would be helpful!
Thanks,
Matt