The dreaded conveyor belt problem

In summary: Well, it's true that the power is 1620 Watts at any instant in time, but the question was asking for the power required to operate the conveyor belt. This implies that you want the total power needed to keep the conveyor belt moving at a steady speed of 4.5 m/s while continuously pouring gravel onto it at a rate of 80 kg/s. So, you need to find the average power required. And since the power is constantly changing, you need to integrate over time to get the average power.That is where the 810 Watts comes in. It is the average power required to operate the conveyor belt at a steady speed of 4.5 m/s while continuously pouring gravel onto it at a rate of
  • #1
2,178
0
Not too hard I guess. Just wondered if I am correct.

question:

Gravel is continiously being poured at the rate dm/dt = 80kg/s on a conveyor belt moving at 4.5 m/s. What is the power required to operate the conveyor belt?

my answer:

power required = work done on the gravel per second=ma(v)

v = velocity of the conveyor belt.

so

P=80.0 kg/s * 4.5 m/s * 4.5 J/s =1620 Watts

Now I have a problem with my formula.
will this give me watts or some other unit of measurement?

also, is the problem even close to being correct?

thanks in advance all.

M2k
 
Physics news on Phys.org
  • #2
Hi, and welcome to PF.

Originally posted by mighty2000
Gravel is continiously being poured at the rate dm/dt = 80kg/s on a conveyor belt moving at 4.5 m/s. What is the power required to operate the conveyor belt?

my answer:

power required = work done on the gravel per second=ma(v)

Not quite. The power is a force times a velocity. The velocity is the velocity of the belt (because that is what you are trying to move. What is the force? It comes from the stream of matter hitting it. In this case,

F=(dm/dt)*u

where u=the velocity of the gravel as it hits the belt. You have not provided information on this, and it is needed to solve the problem.

Maybe you left something out?

P=80.0 kg/s * 4.5 m/s * 4.5 J/s =1620 Watts

Where did the 4.5 J/s come from?

Now I have a problem with my formula.
will this give me watts or some other unit of measurement?

No, the units are not right. J/s=Watts.

also, is the problem even close to being correct?

No; make the corrections above and you will be OK.
 
  • #3
Thanks for the reply Tom. You say that u is needed to solve the problem but that is the problem. Is there another approach that I need to take to solve this then? And I did leave something out. What is the power required to operate the conveyor in watts.

Thanks

M2k
 
Last edited:
  • #4
Ok I think I may have it.

if watts are in units of J/s then the change in KE vs time would equal the power in watts.

thus:

dKE/dt = 1/2 dm/dt Vcb^2

=(.5)(80)(4.5)^2 = 810 J/s or 810 Watts.

which is half of the gravel's rate of change of momentum in the horizontal direction.

Any Ideas?

Thanks

M2k
 
  • #5
anybody have an opinion on my latest post?

Thanks
 
  • #6
I did it like this, but I'm not sure if it's correct.

Like Tom said: P=F*v

and F=dp/dt with p=m*v
but here m is time-dependant and v is constant.
So: F=dp/dt=dm/dt*v
and P=80*4.5^2=1620 Watts
 
  • #7
Looks fine to me.
 
  • #8
Yeah, I already figured out the answer. I got 1620 too using the same method.


thanks for the reply, Peace out
 
Last edited:
  • #9
I think 810 is the right answer, via two approaches:

(a) I think mighty2000's derivation yielding 810 Watts is nearly correct:

The final kinetic energy of a mass m of gravel is (1/2) m v2. If we presume it started at rest, then the net work done at time t is (letting t = 0 be when the first particle of gravel has reached speed v):

W(t) = (1/2) m(t) v2 + C

Where C is a constant that equals the work done on the gravel that hasn't quite been accelerated to v. (C is a constant because dm/dt is a constant, so the only difference between the picture at two different times is the amount of mass that has already reached speed v)

Differentiating WRT time gives:

P = (1/2) dm/dt v2 = 810 Watts


(b) Instantaneous power is the product of force and instantaneous velocity. Average power is the product of force and average velocity. If we presume a constant force is applied to bring individual gravel particles up to speed from rest, then the average velocity is half the final velocity, so the average power is P = F (1/2 v_max) = 1/2 * 1620 Watts = 810 Watts. (If we presume nonconstant force, we get a fun integral that will also result in 810 Watts)

Hurkyl
 
Last edited:
  • #10
GSRX720 was correct in his explination:

F=dp/dt with p=m*v
but here m is time-dependant and v is constant.
So: F=dp/dt=dm/dt*v
and P=80*4.5^2=1620 Watts

so 1620 is the correct answer. Thanks for the vote of confidence though



peace out M2k
 
Last edited:
  • #11
Hrm. What is the source of the answer?

Hurkyl
 

Suggested for: The dreaded conveyor belt problem

Back
Top