Original Question: A person doing a chin-up weighs 700N exclusive of the arms. During the first 25.0 cm of the lift, each arm exerts an upward force of 355N on the torso. If the upward movement starts from rest, what is the persons velocity at the point.

some work:
700-2(355) = 10 N
W = 25 cm *10 N
.25M*10N= 2.5 J
(Mass ~ 700N = 9.8[M] )
A = 2.5 / 71.4
=.035 m/s

My question: so what do I do now with this .035 m/s?

Cyclovenom
Sep28-04, 07:13 PM
Try using W = \Delta K

Sirus
Sep28-04, 08:39 PM
You could also find acceleration using F_{net}=ma then use kinematic formulas to find final velocity.