How Long Does It Take to Build a Nuclear Power Plant?

Click For Summary
SUMMARY

The construction timeline for a nuclear power plant, particularly for the Westinghouse AP600/AP1000, is estimated to be around 36 months under optimal conditions, although a more realistic timeframe is 4-6 years. The lengthy construction periods historically, such as the 25 years for the last reactor in the U.S., were largely due to complications in the licensing process, which has since been reformed. New regulatory procedures now allow for separate licensing of reactor designs before construction begins, aiming to streamline the process and reduce delays caused by public debates and legal challenges.

PREREQUISITES
  • Understanding of nuclear reactor types, specifically Westinghouse AP600/AP1000
  • Familiarity with the U.S. nuclear regulatory framework and licensing processes
  • Knowledge of construction project management principles
  • Awareness of supply chain issues related to nuclear components like piping and pressure vessels
NEXT STEPS
  • Research the updated U.S. Nuclear Regulatory Commission (NRC) licensing procedures
  • Explore the implications of the two-step licensing process for nuclear power plants
  • Investigate supply chain management for nuclear components and their fabrication locations
  • Study the historical context of nuclear plant construction timelines and delays
USEFUL FOR

Nuclear engineers, project managers in the energy sector, regulatory affairs specialists, and policymakers interested in nuclear energy development and its regulatory landscape.

Pengwuino
Gold Member
Messages
5,109
Reaction score
20
How long does it take for a nuclear power plant to be built and to have its first reactor come on line? Let's start the time line at basically when the permit is requested and end it when the first reactor goes fully online. What kind of time period are we looking at there in the best case scenarios with no massive interuptions or complications occurring?
 
Engineering news on Phys.org
Pengwuino said:
How long does it take for a nuclear power plant to be built and to have its first reactor come on line?
There are claims of 36 months for the new Westinghouse AP600/AP1000. The last reactor unit to come online in the United States took 25 years to build.
 
Well I wouldn't suppose that all nuclear power plants take 25 years to make just as I wouldn't suppose a claim would be very accurate as to the average time it would normally take.
 
http://www.tvo.fi/486.htm

We should've our latest up 2009, the final ok for building came around mid 2002. It's a third unit for this plant, but basically they're building it as a separate one.
 
Last edited by a moderator:
36 months may be optimistic, but it is believable from the point of starting construction to going critical. The reason a lot of plants took a long time was due to weaknesses in the licensing process allowing for interruptions and delays at many junctures. This increases construction time and drives up costs substantially.

New regulatory procedures are in place to hopefully reduce this occurrence. For instance, the reactor design is licensed separately and before the plant is built, and there are set time periods for public debate.
 
hitssquad said:
There are claims of 36 months for the new Westinghouse AP600/AP1000. The last reactor unit to come online in the United States took 25 years to build.
A period of 36 months is quite optimistic. Probably 4-5 years is more realistic, and perhaps 6 years is even more so.

One problem will be getting the piping and pressure vessels/steam generators. At the present time, these components are fabricated outside the US.

Any plant will be new, and even though the NRC has adopted a simplified licensing process, the utility will probably be cautious.

As for 25 years, I suspect that is a reference to Watts Bar, and this is due to extraordinary circumstances at TVA. They were overextended with multiple plants (including the unfinished Bellefonte units - first B&W plants along RWE's Mulheim-Kaerlich designed to use 17x17 fuel). The management put all the resources into upgrading and restarting Browns Ferry 2 & 3, with BF1 still mothballed. Bellefonte units are history. :frown:
 
BCRion said:
36 months may be optimistic, but it is believable from the point of starting construction to going critical. The reason a lot of plants took a long time was due to weaknesses in the licensing process allowing for interruptions and delays at many junctures. This increases construction time and drives up costs substantially.

New regulatory procedures are in place to hopefully reduce this occurrence. For instance, the reactor design is licensed separately and before the plant is built, and there are set time periods for public debate.

Let me just elaborate some on what BCRion has said.

The licensing process in the USA is a two step process. First the utility applies to build
the plant; an action that can be, and frequently is; challenged in court. After a protracted
period of lawsuits and public comment - the construction permit is granted and the utility
can build the plant. After the plant is constructed, the utility has to apply for an
operating license; and the whole process - lawsuits and all, questioning whether the plant
should even exist; starts all over again.

Can you imagine building your home in such circumstances? You convince all the zoning
boards and planning boards that your house will be acceptable to the community and
obtain your building permit. Then after properly construnction the house as per the permit,
and as verified by the building inspector; you would then have to apply for a permit to
actually inhabit the house. During this second permitting process; anybody can challenge
any of the features and siting of the now completed house.

That's the way nuclear power used to be licensed in the USA. The Congress has done
some reform of the laws. Hopefully they have instituted a sensible process for licensing
new reactors.

Dr. Gregory Greenman
Physicist
 

Similar threads

Replies
7
Views
3K
  • · Replies 10 ·
Replies
10
Views
3K
  • · Replies 2 ·
Replies
2
Views
2K
Replies
5
Views
5K
Replies
25
Views
6K
  • · Replies 52 ·
2
Replies
52
Views
10K
  • · Replies 20 ·
Replies
20
Views
3K
  • · Replies 6 ·
Replies
6
Views
20K
  • · Replies 13 ·
Replies
13
Views
3K
  • · Replies 5 ·
Replies
5
Views
6K