Calculating backlog in quarters

  • Thread starter Thread starter Huumah
  • Start date Start date
Click For Summary
The discussion focuses on calculating backlog over six quarters given a production capacity of 25 units per quarter against a demand of [29, 24, 32, 21, 31, 21]. The user seeks clarification on how to accurately account for backlogs, especially when production figures drop below zero, which raises confusion about the meaning of negative production. It is noted that the total demand exceeds the total possible production, resulting in an inevitable backlog of at least 8 units. The conversation emphasizes the importance of understanding backlog management policies, as the approach to filling backlogs can vary significantly. More specific information about the objectives and policies is needed to provide a clearer solution.
Huumah
Messages
27
Reaction score
0
Mod note: Moved from a technical math section, so the template doesn't appear.
Hi

I have a demand for 6 quarters of [29, 24,32,21,31,21] and can produce 25 units each quarter.

I am trying to calculate how many units I have to deliver at least 1 quarter too late and also how many units I deliver at least 2 quarters too late.

Is my table correct ? I get so confused when I get to a production of <0.

How can i calculate the ones that are at least one quarter too late and at least 2 quarters too late?

Code:
Demand    Production    Backlog
    -------------------------------
    29          25             4
    24          21             3
    32          18             14
    21          4              17
    31          -13            44
    21          -57            78
 
Last edited by a moderator:
Physics news on Phys.org
Huumah said:
Hi

I have a demand for 6 quarters of [29, 24,32,21,31,21] and can produce 25 units each quarter.

I am trying to calculate how many units I have to deliver at least 1 quarter too late and also how many units I deliver at least 2 quarters too late.

Is my table correct ? I get so confused when I get to a production of <0.

How can i calculate the ones that are at least one quarter too late and at least 2 quarters too late?

Code:
Demand    Production    Backlog
    -------------------------------
    29          25             4
    24          21             3
    32          18             14
    21          4              17
    31          -13            44
    21          -57            78
In the first quarter, what happens to the backlog of 4? Does it get added to the demand for the next quarter? If it does, your table doesn't show it.

How can production be negative? You can produce 15 things or 0 things, but what does it mean to produce -13 things?
 
Is this a homework problem?
 
Huumah said:
Mod note: Moved from a technical math section, so the template doesn't appear.
Hi

I have a demand for 6 quarters of [29, 24,32,21,31,21] and can produce 25 units each quarter.

I am trying to calculate how many units I have to deliver at least 1 quarter too late and also how many units I deliver at least 2 quarters too late.

Is my table correct ? I get so confused when I get to a production of <0.

How can i calculate the ones that are at least one quarter too late and at least 2 quarters too late?

Code:
Demand    Production    Backlog
    -------------------------------
    29          25             4
    24          21             3
    32          18             14
    21          4              17
    31          -13            44
    21          -57            78

I cannot figure out what you are attempting to do; your problem description makes no sense to me.

Basically, you have a total 6-quarter demand of 29 + 24 + ... + 21 = 158, and a maximum possible 6-month production of 6*25 = 150. Therefore, no matter what you do you will have a total backlog of 158 - 150 = 8, and it will be even higher if you produce less than 25 in any quarters. Then, exactly what happens to the backlogs depends on the backlog-filling policy. For example, if you fill as much of previous backlogs as soon as possible, you can produce 25 in each of quarters 1,2, using 4 units of the Q2 production to fill the 4 units backlogged from Q1; that will leave 21 units available to meet Q2 demand, so you will end Q2 with a backlog of 24 - 21 = 3 units, etc.

There are, of course, other policies possible, but since you do not specify any objective (such as minimization of some type of penalty cost), it is impossible to narrow it down to a single policy. You need to specify more information.
 
Last edited:
Ray Vickson said:
You need to specify more information.
Yes.
 

Similar threads

  • · Replies 11 ·
Replies
11
Views
2K
Replies
4
Views
2K
Replies
1
Views
2K
  • · Replies 3 ·
Replies
3
Views
2K
  • · Replies 45 ·
2
Replies
45
Views
4K
Replies
1
Views
1K
  • · Replies 1 ·
Replies
1
Views
1K
  • · Replies 4 ·
Replies
4
Views
3K
  • · Replies 18 ·
Replies
18
Views
3K
  • · Replies 2 ·
Replies
2
Views
2K