Solve Inverse Proportion Road Works in 14 Days

  • Thread starter Thread starter LiHJ
  • Start date Start date
  • Tags Tags
    Inverse
Click For Summary
SUMMARY

The problem involves calculating the total time required to complete road repairs when additional workers are introduced after a certain period. Initially, 4 workers can complete the task in 42 days, equating to 168 worker days. After 14 days of work, where only 4 workers are active, they complete 56 worker days of work, leaving 112 worker days remaining. With 14 workers available after the first 14 days, the remaining work can be completed in an additional 8 days, resulting in a total of 22 days to finish the project.

PREREQUISITES
  • Understanding of inverse proportion and worker productivity
  • Basic algebra for solving equations
  • Familiarity with the concept of "worker days" as a unit of labor
  • Knowledge of how to calculate fractions of work completed
NEXT STEPS
  • Study the concept of inverse variation in mathematical problems
  • Learn how to calculate work done using the formula for worker days
  • Explore real-world applications of workforce management and productivity
  • Practice similar problems involving multiple phases of work and varying workforce sizes
USEFUL FOR

Students studying mathematics, educators teaching problem-solving techniques, and professionals in project management or workforce planning who need to optimize labor resources.

LiHJ
Messages
43
Reaction score
2

Homework Statement


Dear Mentors and PF helpers,

Please help me with this question as my junior asked me but I have some doubts in it:

It takes 4 workers to complete repairing the road in 42 days. Suppose that 14 days into the road works, 10 more workers are brought into help out in the road works. Calculate the total number of days needed to complete the road works in this case.

Homework Equations



y = k/x , where k is a constant and y and x are variables [/B]

The Attempt at a Solution


let y be days and x be number of workers
42 = k / 4
168 = k

From the question they trying to ask if during the 14 days of work with 14 men but after this 14 days it's going to be 4 men working again.

Suppose there are 14 workers ("10 more workers are brought into help..."):

d = 168 / 14 = 12

It takes 12 days to complete the repairing, but why the question says " Suppose that 14 days into the road works ..."

Can anyone help me? Thank you for your time.
 
Physics news on Phys.org
LiHJ said:
From the question they trying to ask if during the 14 days of work with 14 men but after this 14 days it's going to be 4 men working again.

No. I think there are 14 days of work by 4 men. Then 14 men work to finish the road.First find the rate R at which 1 worker works. Use the fact that 4 men working at that rate can finish 1 road in 42 days.

(4 workers) (R) (42 days ) = 1 road

Solve for R

Then write the equation that says 14 men working at rate R for X days build 1-(4)(R)(14) of the road.
 
LiHJ said:

Homework Statement


Dear Mentors and PF helpers,

Please help me with this question as my junior asked me but I have some doubts in it:

It takes 4 workers to complete repairing the road in 42 days. Suppose that 14 days into the road works, 10 more workers are brought into help out in the road works. Calculate the total number of days needed to complete the road works in this case.

Homework Equations



y = k/x , where k is a constant and y and x are variables [/B]

The Attempt at a Solution


let y be days and x be number of workers
42 = k / 4
168 = k
And what does k represent?
LiHJ said:
From the question they trying to ask if during the 14 days of work with 14 men but after this 14 days it's going to be 4 men working again.

Suppose there are 14 workers ("10 more workers are brought into help..."):

d = 168 / 14 = 12

It takes 12 days to complete the repairing, but why the question says " Suppose that 14 days into the road works ..."

Can anyone help me? Thank you for your time.
Your approach needs to be more systematic, taking into account that for the first 14 days only 4 men are working on the road, and then after that, an additional 10 men are working on it. What fraction of the job can the first four men do in the first 14 days? From this, what fraction of the job can each man do per day, assuming that all four men work at the same rate? How much of the job is left after the first 14 days? How long will it take for all of the men (all 14 of them) to finish the job?
 
Thank you Stephen and Mr Mark.

Here's my working:

If the job is to be done by 1 day, it will need 42 x 4 = 168 workers.
So first is being done by 4 men in 14 days, so is like 56 workers already did their part.
Left over work is 168 - 56 = 112 workers still needed to complete it.
Number of days left = 112/ 14 = 8 days
So total number of days required = 14+8 = 22 days
 
I agree, except that I would change the words slightly. The unit of labor is "worker days" (similar to the idea of "man hours").

If 1 road is built by 4 men in 42 days, it will need 42 x 4 = 168 worker days.
The first phase is being done by 4 men in 14 days, they accomplish 56 worker days..
Left over work is 168 - 56 = 112 worker days still needed to complete it.
Number of days left to finish the job = 112/ 14 = 8 days
So total number of days required = 14+8 = 22 days
 

Similar threads

Replies
3
Views
2K
  • · Replies 1 ·
Replies
1
Views
2K
  • · Replies 4 ·
Replies
4
Views
2K
  • · Replies 6 ·
Replies
6
Views
2K
  • · Replies 11 ·
Replies
11
Views
2K
  • · Replies 3 ·
Replies
3
Views
2K
Replies
4
Views
2K
  • · Replies 69 ·
3
Replies
69
Views
10K
  • · Replies 6 ·
Replies
6
Views
2K
  • · Replies 4 ·
Replies
4
Views
2K