nikkkom
Gold Member
- 2,074
- 397
zapperzero said:Large tanks of what, please?
Water.
zapperzero said:Large tanks of what, please?
nikkkom said:Safety versus meltdown can be achieved only by designing in very robust emergency cooling systems. In my "armchair engineer" view, something like "reactor sitting in a stainless steel lined pit with no drains, and with a set of large tanks beside it which can be manually drained into the pit, no electricity needed" should work.
jim hardy said:You just described PWR "Acumulators".
Kutt said:Speaking of, is it possible to bring in more diesel fuel to nuclear power plants by the truckload in case the emergency diesel generators run dry?
nikkom said:What I described are tanks which can, if all else fails, flood reactor pit and submerge the reactor, i.e. cool reactor from the outside.
Kutt said:There should be robust "last resort" emergency cooling systems which can be manually operated by hand without electricity to supply the reactor with water. If such systems existed at Fukushima, the safety and stability of the reactors would have been ensured.
More water can be brought in via truck or helicopter if needed.
Speaking of, is it possible to bring in more diesel fuel to nuclear power plants by the truckload in case the emergency diesel generators run dry?
The roads leading to the Fukushima Daiichi NPP were blocked by debris from the Tsunami, making this impossible.
jim hardy said:Fair enough. You're suggesting a passive containment flood system.
Ours was active not passive and used pumps. It was intended to reduce containment pressure, it fed spray nozzles in upper containment near ceiling ..
Our accumulators were pressurized to about 1/3 reactor operating pressure so they'd flood vessel while pressure is on the way down following a break.
Fukushima operators might have been able to depressurize had they done it very early. It is suggested in the ORNL station blackout study to do that.
Hindsight is always 20/20...
.....
we kept 30 days diesel fuel onsite. Yes, it was trucked in.
The analysis shows, because of the loss of the drywell coolers, that it is necessary
for the operator to begin to reduce the reactor vessel pressure to about
0.791 MPa (100 psig) within one hour of the inception of the Station
Blackout. This depressurization reduces the temperature of the saturated
fluid within the reactor vessel and thereby decreases the driving potential
for heat transfer into the drywell, yet keeps the vessel pressure
high enough for continued operation of the RCIC system steam turbine.
With this action, the drywell average ambient temperature can be kept be
low 149°C (300°F) throughout the initial phase of a Station Blackout;
tests have shown that both the drywell structure and the equipment located
therein can be expected to survive temperatures of this magnitude.
The analysis also reveals an important second reason for operator action to
depressurize the reactor vesel early in the initial phase of a
Station Blackout. This depressurization removes a great deal of steam and
the associated stored energy from the reactor vessel at a time when the
RCIC system is available to inject replacement water from the condensate
storage tank and thereby maintain the reactor vessel level. Subsequently,
when water injection capability is lost for any reason, remote-manual re
lief valve operation would be terminated and there would be no further
water loss from the reactor vessel until the pressure has been restored to
the setpoint [7.72 MPa (1105 psig)] for automatic relief valve actuation.
Because of the large amount of water to be reheated and the reduced level
of decay heat, this repressurization would require a significant period of
time. In addition, the subsequent boiloff* would begin from a very high
vessel level because of the increase in the specific volume of the water
as it is heated and repressurized. Thus, an early depressurization will
provide a significant period of valuable additional time for preparative
and possible corrective action before core uncovery after injection capability is lost.
**The term "boiloff" is used to signify a monotonic decrease in reactor vessel water level due to intermittent loss of fluid through the
primary relief valves without replacement.
vxx
jim hardy said:As I've said i never spent any time around BWR's , just walked through one once.
I went by this report, which is an analysis and re-thinking of station blackout scenarios done around 1981. They used Brown's Ferry's design as their case study. I stumbled across it while following events at Fukushima on another forum. It's been posted here at PF back in 2011.
http://www.ornl.gov/info/reports/1981/3445600211884.pdf
I'm not a BWR guy.
If you are one, you are certainly more versed than i in their station blackout approach . old jim
Kutt said:Dang, I forgot that the Fukushima reactors had to be depressurized before any water could to be injected. The safety relief valves located inside the PCV were stuck shut and could not be operated because of the crushing pressure (thousands of PSI) inside the primary containment vessel pushing against the exterior of the safety relief valves.
![]()
Hiddencamper said:Containment pressure in the Mark I containment system only goes up to about 125-140 PSI. Around that point you either have your rupture disks blow (for the Japanese containment systems), or your penetrations and seals start to fail, causing pressure leakoff (likely one mode through which hydrogen migrated into the secondary containment building).
And not all of the relief valves issues were due to containment differential pressure. Between loss of DC power allowing solenoids to go back to the closed position during the event, some unique behaviors of the SRVs in general, and difficulties establishing portable air supplies to the SRVs, there were a number of reasons the SRVs had trouble.
The SRVs are designed to lift against the design containment pressure several times without being recharged, and should be capable of doing at least 1-2 lifts against double containment design pressure (which is what the Fukushima containments were getting up to). Leakage of the system, constant use of the SRVs, and inability to restore the Instrument Air Supply to recharge the SRVs was really what prevented the valves from opening/staying open. A higher containment pressure does require higher accumulator pressure to lift the SRVs, but it doesn't prevent the SRVs from lifting.
And a final note, this isn't just the "Fukushima reactors", of which you are referring to the BWR series of reactors, but this is an attribute of virtually all light water commercial power reactors, including PWRs.
Perhaps you should try calculating how many thousands of people cranking by hand would be required to pump enough water to cool a nuclear reactor...Kutt said:There should be robust "last resort" emergency cooling systems which can be manually operated by hand without electricity to supply the reactor with water. If such systems existed at Fukushima, the safety and stability of the reactors would have been ensured.
russ_watters said:Perhaps you should try calculating how many thousands of people cranking by hand would be required to pump enough water to cool a nuclear reactor...
Kutt said:The pipework which supplied emergency pressurized air to the SRV's were severely damaged in the earthquake and rendered useless.
Kutt said:What about a massive water tank that feeds water into the reactor (using gravity) which can activated by turning some valves?
Hiddencamper said:I assume we are talking about the instrument air system. Do you have a link to this, I do not recall seeing any absolute data suggesting this was the case, especially because SRVs were used in units 2 and 3 to support blowdown and transition to portable pumping equipment, which implies the IA system was not damaged.
Some info about IA, it is a non-safety system. It automatically isolates (shuts/locks out) on loss of power, and requires specific manual interlock overrides in order to restore it. I'm not sure if the IA system actually failed or if there were more complicated events and I would appreciate a source. Thanks.
Kutt said:I remember seeing a two-hour long docu-drama about the Fukushima incident with actors re-creating the events. It also went into technical detail to how the pipework which supplied the SRV's with enough pressurized air to open, were damaged and rendered inoperable by the earthquake.
I watched this documentary on youtube, but so far, I haven't been able to find it again.
I'll keep looking.
And there were two types of accumulators for the SRV, one for the relief valve (85L) and the other for the ADS (250L). Both of them were installed inside the PCV. Normally, nitrogen for the relief valve accumulator was supplied from the liquid nitrogen system (AC) line, and nitrogen for the ADS accumulator was supplied from the nitrogen cylinder. The pressure gauge set at each supply line was scheduled to be checked daily by the shift team who were on duty between 15:00 and 21:00. However, because the isolation valve of the supply line to the accumulator had closed due to external power loss after the tsunami, the supply to the accumulator had not been carried out as they were unable to do so. For this reason, the residual pressure that allowed the pressure to be applied to the SRV was the relief valve accumulator, ADS accumulator, and pressure remaining in the piping between the isolation valve (which had closed) and the accumulator side
Hiddencamper said:I wouldn't trust a youtube documentary.
Looking at the official report
http://www.cas.go.jp/jp/seisaku/icanps/eng/02Attachment1.pdf
it looks like loss of power caused an isolation of the instrument air system, which was not recoverable due to AC power being lost, and that the accumulators were depleted.
In other words, the earthquake did NOT cause the recharging system to fail. Instead, the inability to open the isolation valves caused the issue. Even if the system did fail, it is not safety-grade and is not expected or required to operate post accident (although it probably should be).
jim hardy said:Fukushima operators might have been able to depressurize had they done it very early. It is suggested in the ORNL station blackout study to do that.
Hindsight is always 20/20...
nikkkom said:Water.
Hiddencamper said:With regards to depressurizing, you actually DONT want to depressurize the RPV in a Fukushima type situation.
BWRs can utilize high pressure reactor steam to operate their RCIC, IC, or HPCI systems for extended core injection.
While these systems do not provide for decay heat removal, you can achieve that function through early containment venting and portable pump injection.
If you have no low pressure coolant injection pumps available, once you depressurize, you lower the water level remaining in the core (generally uncovering the fuel), and you lose ALL injection.
I've been involved with Fukushima responses for BWRs if anyone is interested on how the plants actually respond, and what we are doing and changing to respond to Fukushima-like situations.
Or you can depressurize and use the same portable pump to inject to *RPV* instead of the more complex setup you describe.
RCIC is useful for delaying the meltdown. Useful, but not enough.
I want to have a system which pretty much *guarantees* to prevent meltdowns. Which means passive, power-independent system. Which means it should be gravity-fed. Which means very low pressure. Which means it can't inject water into pressurized PCV or RPV. Which means they need to be depressurized in order to allow this water to go in.
Are filters being installed on vent lines?
Emergency lighting is a fire-code thing. I can't speak for all plants, but at the plant I'm at now, and the few I've been at, emergency lights have individual lighting packs. The lights are separated into "normal" emergency lighting, and b.5.b emergency lighting, which is accredited for beyond design basis events where there are explosions and other significant site damage. Only b.5.b lighting would be assumed to function during a Fukushima-like event. There are b.5.b storage lockers with credited lights and equipment for operators to use in the event that all normal and emergency lighting and systems are lost. The emergency lights have their own backup batteries, and there are reserve batteries on site.Do you have battery-backed lighting? Individual batteries in each light, or what?
Do your operators now know how to open the vent? Did they practice it? Without electricity
Do you have gravity-feed water sources?
The more I learn here, the scarier it looks. Safety relief valves need something (compressed air) to work? *Safety* valves? Really? Why? It's not possible to have valves which are actuated solely by the pressure they are intended to relieve??
That wasn't my intent at all... sometimes what i don't say gets me in more trouble than what i do say...nikkkom said:Fukushima operators can be hardly blamed for it. Someone else should be held responsible.
That the plants had not considered and addressed station blackout in their procedures and training falls on some level of management. Those ORNL blackout analyses were around for nearly two decades. One doesn't wait for regulators to make you do something that important. We drilled on station blackout in our simulator.Someone wrote accident manual which said that loss of all power is impossible (!).
They are standard emergebcy equipment. Our batteries were 125 volt so they were plain rough service incandescent lightbulbs. (Now there's an interesting thought - EPA wants to outlaw incandescents.)Someone decided that battery-backed lights are an unnecessary luxury in a nuclear power plant (what can possibly go wrong?).
Had your first two issues been addressed, things wouldn't have got so far as to need such filters.Someone didn't think about installing filters on emergency vent lines. Someone didn't think about training operators how to open said vents.
Yep. Placing diesels in basement made them safer from earthquakes but left them vulnerable to flooding.Operators were left in the dark, figuratively as well as literally. And wet.
The scary thought is that F1 would have melted down on any given day during last 40 years, if tsunami would happen on that day.
Hiddencamper said:>> Or you can depressurize and use the same portable pump to inject to *RPV* instead of the more complex setup you describe.
The issue here, is that you have to assume the plant has already gone 8+ hours without electricity.
Pretty much the ESBWR design. Take a look at it. The problem is you are limited based on the size of your initial pools (which is limited based on the design and cost of the structural loading on your containment, as the pools are all seismic class 1).
The RELIEF mode is power actuated utilizing a pneumatic air supply.
The SRVs are in the containment and are connected to the main steam system. Because they are part of the ASME class 1 piping, they must be within containment. This pretty much eliminates any possibility of a person going in and manually lifting the valve, even if such a design existed.Stupid question: is it impossible to have relief valves which can be operated manually?
Fukushima demonstrated a different scenario. When tsunami receded, even though operators were without power for only a few minutes so far, they *knew* that power is likely to be unavailable for days.
If at that moment they would have a way and training how to depressurize RPV and if they would have low-pressure injection source (like fire truck), they could just do that: keep RPV filled, at ~100 C and at ~1 atm. KISS. No RCIC. No need to think about temperature/pressure in the torus. (They wouldn't even absolutely need vent to be filtered, because the steam at that point was relatively uncontaminated).
Hiddencamper said:The SRVs are in the containment and are connected to the main steam system. Because they are part of the ASME class 1 piping, they must be within containment. This pretty much eliminates any possibility of a person going in and manually lifting the valve, even if such a design existed.
Additionally, a portable pump only provides injection, it does not support decay heat removal.
You also cannot just "sit at 100 lbs" or 1atm of pressure. The SRVs are not control systems. They are either "OPEN" or "CLOSED". If you leave 1 SRV open, with a shut down core, your pressure will continue dropping to 0.
the operators have to manually open and close them