How many days will it take B to finish the remaining work?

  • Context: MHB 
  • Thread starter Thread starter mathdad
  • Start date Start date
  • Tags Tags
    Application Work
Click For Summary

Discussion Overview

The discussion revolves around a work completion problem involving two individuals, A and B, who work together for a period before one leaves. Participants explore how to calculate the time it will take for B to finish the remaining work after A departs. The conversation includes mathematical reasoning and equations related to work rates and completion times.

Discussion Character

  • Mathematical reasoning
  • Technical explanation
  • Debate/contested

Main Points Raised

  • Some participants propose using the equation \( \frac{1}{25} + \frac{1}{30} = \frac{1}{T} \) to determine the time T it takes for A and B to complete the work together.
  • Others argue that calculating the least common multiple (LCM) of their work rates can help find how much work is done in a given time frame.
  • A few participants express confusion regarding the logic of the calculations presented, indicating a need for clarity on how much work remains after 5 days of collaboration.
  • One participant calculates T as \( \frac{150}{11} \) days, which is derived from their combined work rates.
  • Another participant notes that if 19/30 of the job remains, it can be calculated how long it will take B to complete that portion based on his work rate.
  • Multiple participants arrive at the conclusion that B will take 19 days to finish the remaining work, but this is presented as a consensus rather than an established fact.

Areas of Agreement / Disagreement

While some participants agree on the calculations leading to B taking 19 days to complete the remaining work, there is still uncertainty and confusion about the initial logic and equations used, indicating that the discussion remains partially unresolved.

Contextual Notes

Participants have not fully clarified all assumptions regarding the work rates and the implications of the equations used. There may be dependencies on definitions of work completion that are not explicitly stated.

mathdad
Messages
1,280
Reaction score
0
A can do a piece of work in 25 days and B can do the same work in 30 days. They work together for 5 days and then A leaves. B will finish the remaining work in...

a) 21 days
b) 11 days
c) 20 days
d) 19 days

Is the following equation correct?

1/25 + 1/B = 1/5
 
Mathematics news on Phys.org
RTCNTC said:
A can do a piece of work in 25 days and B can do the same work in 30 days. They work together for 5 days and then A leaves. B will finish the remaining work in...

a) 21 days
b) 11 days
c) 20 days
d) 19 days

Is the following equation correct?

1/25 + 1/B = 1/5

I would first look at:

$$\text{lcm}\,(25,30)=150$$

We observe that in 150 days, A can complete 6 tasks and B can complete 5 tasks, and so working together they can complete 11 tasks in 150 days. The means that working together they can complete one task in 150/11 days. So, if they work together for 5 days, what portion of the task remains to be done?
 
I don't follow the logic.
 
RTCNTC said:
I don't follow the logic.

In order to answer this question, we need to know how long it takes A and B working together to complete one task, because we need to know how much of the task will be remaining after 5 days. We'll call this length of time T. Instead of the method I presented, we could also write:

$$\frac{1}{25}+\frac{1}{30}=\frac{1}{T}$$

This equation arises from looking at what gets done in 1 unit of time (days in this problem). In 1 day, A can complete 1/25 of a task and B can complete 1/30 of a task, and so the LHS of the equation represents their combined effort in 1 day. Since we've defined T to be the amount of time it takes A and B to complete a task working together, their combined efforts for 1 day, must equal 1/T.

What do you get when you solve for T?
 
MarkFL said:
In order to answer this question, we need to know how long it takes A and B working together to complete one task, because we need to know how much of the task will be remaining after 5 days. We'll call this length of time T. Instead of the method I presented, we could also write:

$$\frac{1}{25}+\frac{1}{30}=\frac{1}{T}$$

This equation arises from looking at what gets done in 1 unit of time (days in this problem). In 1 day, A can complete 1/25 of a task and B can complete 1/30 of a task, and so the LHS of the equation represents their combined effort in 1 day. Since we've defined T to be the amount of time it takes A and B to complete a task working together, their combined efforts for 1 day, must equal 1/T.

What do you get when you solve for T?

I got T = 150/11.
 
RTCNTC said:
I got T = 150/11.

Yes, and so if A and B have worked together for 5 days, the portion of the job remaining would be:

$$\frac{\dfrac{150}{11}-5}{\dfrac{150}{11}}=?$$
 
I got 19/30.
 
RTCNTC said:
I got 19/30.

Good...and so if 19/30 of the job remains and it takes B 30 days to complete the entire task, how long will it take for B to complete the 19/30 of the task that remains?
 
(19/30)(30) = 19 days
 
  • #10
RTCNTC said:
(19/30)(30) = 19 days

Yes...I concur. :D
 

Similar threads

  • · Replies 15 ·
Replies
15
Views
2K
  • · Replies 7 ·
Replies
7
Views
2K
Replies
7
Views
2K
  • · Replies 12 ·
Replies
12
Views
1K
  • · Replies 5 ·
Replies
5
Views
2K
  • · Replies 1 ·
Replies
1
Views
2K
Replies
2
Views
2K
  • · Replies 3 ·
Replies
3
Views
2K
  • · Replies 7 ·
Replies
7
Views
2K
  • · Replies 2 ·
Replies
2
Views
1K