Solving the Time Needed for A & B to Complete a Job Alone

In summary: And then you solved the problem as if A takes half as long as B.$\frac{1}{x}+\frac{1}{2x} = \frac{3}{2x}$Is that the same as $\frac{1}{2x}$?
  • #1
paulmdrdo1
385
0
1. A’s rate of doing work is three times that of B. On a given day A and B work together for 4 hours; then B is called away and A finishes the rest of the job in 2 hours. How long would it take B to do the complete job alone?

if I let x = B's rate of work and 3x = A's rate of work, I'll have this equation,

$\displaystyle 4\left(\frac{1}{x}+\frac{1}{3x}\right)+2\frac{1}{x}=1$

then, $x=7\frac{1}{3}$ and $3x=22$ is this correct?

2. A and B working together can complete a job in 6 days. A works twice as fast as B. How
many days would it take each of them, working alone, to complete the job?

let x = required time for B to finish a job alone, 2x = required time for A to finish a job alone

$\displaystyle 6\left(\frac{1}{x}+\frac{1}{2x}\right)=1$

the answer is x = 9 days for B, and 2(9)= 18 days for A.

but this doesn't make sense. if A is twice as fast as B it will take A lesser time to complete a job than B.

please help.
 
Last edited:
Mathematics news on Phys.org
  • #2
Hello, paulmdrdo!

1. A’s rate of doing work is three times that of B. On a given day A and B work together for 4 hours, then B is called away and A finishes the rest of the job in 2 hours.
How long would it take B to do the complete job alone?

if I let x = B's rate of work and 3x = A's rate of work, I'll have this equation,

$\displaystyle 4\left(\frac{1}{x}+\frac{1}{3x}\right)+2\frac{1}{x}=1$

then, $x=7\frac{1}{3}$ and $3x=22$ is this correct?

Are you sure you know what "rate of work" means?

You have: A's rate of work is [tex]22.[/tex]
What does that mean?

Does it take 22 hours for A to do the job?
Does he get $22 per hour?

Check the original question.
And note that you didn't answer it.
2. A and B working together can complete a job in 6 days.
A works twice as fast as B.
How many days would it take each of them, working alone,
to complete the job?

let x = required time for B to finish a job alone,
2x = required time for A to finish a job alone.
.
So A takes twice as long?

$\displaystyle 6\left(\frac{1}{x}+\frac{1}{2x}\right)=1$

the answer is x = 9 days for B, and 2(9)= 18 days for A.

but this doesn't make sense. if A is twice as fast as B it will take A lesser time to complete a job than B.

please help.

Look at what you wrote.

You said A takes twice as long as B.
 

1. How do you calculate the time needed for A & B to complete a job alone?

The time needed for A & B to complete a job alone can be calculated by using the formula t = AB / (A + B), where t represents the time needed, A represents the time needed for person A to complete the job alone, and B represents the time needed for person B to complete the job alone.

2. What is the significance of knowing the time needed for A & B to complete a job alone?

Knowing the time needed for A & B to complete a job alone can help in determining the efficiency of the team. It can also be used to plan and allocate tasks for individuals or teams in order to meet deadlines and achieve goals.

3. Can the time needed for A & B to complete a job alone change?

Yes, the time needed for A & B to complete a job alone can change depending on various factors such as the complexity of the job, the skills and experience of the individuals, and external factors like resources and equipment.

4. Is it better for A or B to complete the job alone?

It depends on the specific situation. If A has a shorter time needed to complete the job alone, it may be better for them to do it alone. However, if A and B have similar times, it may be more efficient for them to work together and divide the tasks.

5. How can the concept of time needed for A & B to complete a job alone be applied in real life?

The concept of time needed for A & B to complete a job alone can be applied in various fields such as project management, manufacturing, and research. It can also be used in everyday tasks to determine the most efficient way to complete a task or project.

Similar threads

Replies
1
Views
1K
  • General Math
Replies
1
Views
887
Replies
9
Views
1K
Replies
5
Views
1K
Replies
1
Views
881
Replies
7
Views
1K
Replies
1
Views
10K
Replies
5
Views
717
  • General Math
Replies
1
Views
1K
  • General Math
Replies
5
Views
2K
Back
Top