Optimize Work and Time Equations: Formula for Calculating Completion Time"

  • Thread starter Thread starter GlassBones
  • Start date Start date
  • Tags Tags
    Time Work
Click For Summary
The discussion revolves around calculating the completion time for two workers, A and B, using a formula derived from their individual work rates. A completes 80% of a task in 20 days, leading to the conclusion that A can finish the entire job in 25 days, or 1/25 of the work per day. The challenge arises in determining B's work rate based on the remaining 20% of the job completed by both A and B in 3 days. Participants identify errors in the initial equations and clarify that the correct approach involves understanding the contributions of both workers over the specified time. Ultimately, the conversation emphasizes the importance of accurately representing work rates and correcting miscalculations in the formulas used.
GlassBones
Messages
16
Reaction score
1
Homework Statement
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
Relevant Equations
None
I came up with this formula.

A takes 20 days to have 80% completion. Simple algebra gets that A takes 25 days to complete finish by themselves. Now I'm trying to come up with a formula.

##1/.8(1/25) = 1/20## with 80% completion. Now I'm working with the remaining 20%. ## 1/.2(1/25+1/b)##, where b is the total amount of days B takes to finish 1 work. The sum should be 1/23, ie:

##1/.8(1/25)+1/.2(1/25+1/b) = 1/23##

So I should isolate b to find the number of days B takes to finish alone. In doing so I get a negative number...

What's wrong with my reasoning?
 
Physics news on Phys.org
How much work does A do per day as a function of the total work to be done?
 
phinds said:
...as a function of the total work to be done

I know A can complete work alone in 25 days. So 1 day A will do 1/25. Is this what your asking? Sorry just confused
 
GlassBones said:
I know A can complete work alone in 25 days. So 1 day A will do 1/25. Is this what your asking? Sorry just confused

Right. That's usually what you want to do in these problems, is figure out the fraction per day that each person does.

So A working alone does 1/25 of the job in a day.

Now, given that the team of A + B does 0.20 of a job in 3 days, how much of a job does the team of A + B do in one day?

Do you see what knowing that tells you about B's work output?
 
  • Like
Likes GlassBones
GlassBones said:
##1/.8(1/25)+1/.2(1/25+1/b) = 1/23##

So I should isolate b to find the number of days B takes to finish alone. In doing so I get a negative number...

What's wrong with my reasoning?

This does look like it may be doing some of the correct calculations but I can't quite understand your equations.

What does 1/.8 represent? Why are you dividing by the fraction of the job done?

If your first term is equal to 1/20, the reciprocal of the number of days A works, then your second term will be 1/3, the reciprocal of the number of days A + B work together to complete the 0.20 of the job.

But then your equation says (1/20) + (1/3) = (1/23) which is obviously not true.

I think your individual terms on the left are OK, but all you have to do is use the fact that the second term is 1/3. They don't add up to 1/23. And it would be even easier if you worked with the number of days, rather than its reciprocal.
 
  • Like
Likes GlassBones
RPinPA said:
But then your equation says (1/20) + (1/3) = (1/23) which is obviously not true.

...yes there's the issue with my reasoning. I can't believe I made this mistake. Thanks everything makes sense
 
GlassBones said:
phinds said:
How much work does A do per day as a function of the total work to be done?
I know A can complete work alone in 25 days. So 1 day A will do 1/25. Is this what your asking? Sorry just confused
An alternate way to answer @phinds 's question is:

A can do 4% of a whole work in one day.

Then the question can be answered as follows.

The remaining 20% of a whole work takes A&B 3 days to complete of which A does 3 × 4% = 12%.

So in 3 days B did 8% of a whole work.

Let x be the number of days for B alone to do (100% of) a whole work. Then we have the following proportion.

##\displaystyle \frac{8\%}{100\%}=\frac{3}{x} ##
 
You can also compute what percent of the work A has done by the 3rd day and take it from there. B will do the remainder and you can compare the rates.
 

Similar threads

  • · Replies 8 ·
Replies
8
Views
2K
  • · Replies 5 ·
Replies
5
Views
2K
  • · Replies 4 ·
Replies
4
Views
1K
  • · Replies 3 ·
Replies
3
Views
2K
  • · Replies 1 ·
Replies
1
Views
1K
  • · Replies 12 ·
Replies
12
Views
2K
  • · Replies 21 ·
Replies
21
Views
2K
Replies
2
Views
2K
  • · Replies 15 ·
Replies
15
Views
2K
  • · Replies 14 ·
Replies
14
Views
2K