MHB Solving the Time Needed for A & B to Complete a Job Alone

Click For Summary
A's work rate is three times that of B, and after working together for 4 hours, A completes the remaining job in 2 hours. The equation derived indicates that B would take approximately 7.33 hours to finish the job alone. In a separate scenario, A and B can complete a job together in 6 days, with A working twice as fast as B. The calculations suggest B would take 9 days alone, leading to confusion since A should take less time than B, indicating a misunderstanding in the setup of the problem. Clarification on the rates and time taken is needed to resolve the discrepancies.
paulmdrdo1
Messages
382
Reaction score
0
1. A’s rate of doing work is three times that of B. On a given day A and B work together for 4 hours; then B is called away and A finishes the rest of the job in 2 hours. How long would it take B to do the complete job alone?

if I let x = B's rate of work and 3x = A's rate of work, I'll have this equation,

$\displaystyle 4\left(\frac{1}{x}+\frac{1}{3x}\right)+2\frac{1}{x}=1$

then, $x=7\frac{1}{3}$ and $3x=22$ is this correct?

2. A and B working together can complete a job in 6 days. A works twice as fast as B. How
many days would it take each of them, working alone, to complete the job?

let x = required time for B to finish a job alone, 2x = required time for A to finish a job alone

$\displaystyle 6\left(\frac{1}{x}+\frac{1}{2x}\right)=1$

the answer is x = 9 days for B, and 2(9)= 18 days for A.

but this doesn't make sense. if A is twice as fast as B it will take A lesser time to complete a job than B.

please help.
 
Last edited:
Mathematics news on Phys.org
Hello, paulmdrdo!

1. A’s rate of doing work is three times that of B. On a given day A and B work together for 4 hours, then B is called away and A finishes the rest of the job in 2 hours.
How long would it take B to do the complete job alone?

if I let x = B's rate of work and 3x = A's rate of work, I'll have this equation,

$\displaystyle 4\left(\frac{1}{x}+\frac{1}{3x}\right)+2\frac{1}{x}=1$

then, $x=7\frac{1}{3}$ and $3x=22$ is this correct?
Are you sure you know what "rate of work" means?

You have: A's rate of work is 22.
What does that mean?

Does it take 22 hours for A to do the job?
Does he get $22 per hour?

Check the original question.
And note that you didn't answer it.
2. A and B working together can complete a job in 6 days.
A works twice as fast as B.
How many days would it take each of them, working alone,
to complete the job?

let x = required time for B to finish a job alone,
2x = required time for A to finish a job alone.
. So A takes twice as long?

$\displaystyle 6\left(\frac{1}{x}+\frac{1}{2x}\right)=1$

the answer is x = 9 days for B, and 2(9)= 18 days for A.

but this doesn't make sense. if A is twice as fast as B it will take A lesser time to complete a job than B.

please help.
Look at what you wrote.

You said A takes twice as long as B.
 
Here is a little puzzle from the book 100 Geometric Games by Pierre Berloquin. The side of a small square is one meter long and the side of a larger square one and a half meters long. One vertex of the large square is at the center of the small square. The side of the large square cuts two sides of the small square into one- third parts and two-thirds parts. What is the area where the squares overlap?

Similar threads

  • · Replies 1 ·
Replies
1
Views
2K
  • · Replies 5 ·
Replies
5
Views
2K
  • · Replies 1 ·
Replies
1
Views
1K
  • · Replies 1 ·
Replies
1
Views
1K
  • · Replies 9 ·
Replies
9
Views
2K
  • · Replies 7 ·
Replies
7
Views
2K
  • · Replies 5 ·
Replies
5
Views
2K
  • · Replies 5 ·
Replies
5
Views
1K
  • · Replies 3 ·
Replies
3
Views
2K
  • · Replies 4 ·
Replies
4
Views
11K