Some information is hereWe know there are people working there now, what exposure are they subjected to?
ChNPP Radiation Monitoring
a little history
Some information is hereWe know there are people working there now, what exposure are they subjected to?
a.ua. said:
nikkkom said:How badly do you think of Ukraine? I mean, it is not Western Europe, yes, but it isn't a rathole like North Korea either!
Do you really think the reactors would be operated if operating personnel would "show radiation caused health effects"?
African Rover said:Thank you, I am surprised how low the values are.
This is not surprising.African Rover said:Thank you, I am surprised how low the values are.
Since October 1986, in connection with the planned completion of the construction of the "Shelter" and the start of 1.2 units launched massive work on bringing territory of the Chernobyl NPP in reasonable the form
Here's an excerpt from one of the documents.
Government Commission in the aftermath of the accident.
deactivation is obviously not able to fully eliminate radiation contamination and has been implemented on top of filling materials clean contaminated soil followed by asphalting the surface. As a result , in the district of "Shelter " and block 3 entrances to the building and the railroad tracks were below the level of coverage in"In order to reduce the power of gamma radiation in the Chernobyl nuclear power plant ... to develop and implement additional measures to decontaminate areas block number 3 and number 4, and the area adjacent to the plant (including construction base and warehouses)...
Task force of the USSR Ministry of Railways to provide a daily supply of the Southwest and the Lviv railway flatcars at 10 st.Kamenets-Podolsky, and Rock-Podolsky to deliver concrete mix to st.Tolsty Forest ..
Task force of the USSR Ministry of Defense to allocate 100 personnel to perform work on the laying of asphalt mix in the Chernobyl nuclear power plant , 20 vehicles for the transport of the mixture , as well as provide unloading platforms with a mixture of at st.Tolsty Forest and loading it in the vehicle ...
Minavtotransu USSR on October 15 this year allocate 50 vehicles for the delivery of the Chernobyl hot mix ...
USSR State Supply in the bill to allocate funds USSR Ministry of the USSR Mindorstroyu 5000 tons of bitumen to perform the work of asphalting the Chernobyl nuclear power plant. Goskomnefteproduktom USSR put 5 tons of bitumen Mindorstroyu USSR on its application ... "
nikkkom said:That picture does not show any readings on top or inside Unit 4. You can see that two largest readings on the pic are those two closest to it.
IIRC on the Sarcophagus roof gamma field today is around 10 mSv. (That would be 10000 uSv if it would be shown on that picture).
a.ua. said:November 12, 2013 the dismantling of a fifth unit (B-5) vent line 2 (W-2) Chernobyl weighing 48 tons.
and a little joke from people "VKontakte"
a.ua. said:Radiation situation parameters were monitored continuously during the work. Controllable parameters of the radiation situation do not exceed the design control levels.
nikkkom said:I am delighted that radiation was monitored.
However, are we mere mortals not deserving to know the measured levels?
VS-2 dismantling was completed.
Works on dismantling of the ChNPP II Generation Ventilation Stack (VS-2) were completed. 7 blocks with total weight of 330 tons were dismantled according to the Work Execution Plan.
Works on fragmentation of the dismantled blocks are underway within the specially prepared areas. The dismantled fragments are transported to Power Unit No.3 Turbine Hall by special vehicles for temporary storage.
440 fragments have been already placed at the Turbine Hall.
Prior to the placement, the fragments are subject to dust fixation by special compound, and pass the acceptance control for compliance with the criteria of temporary placement at the reserved areas.
http://www.chnpp.gov.ua/index.php?o...demontazh-vt-2-ru&catid=100&Itemid=11&lang=en
http://www.chnpp.gov.ua/index.php?o...utsya-roboti-z-en&catid=100&Itemid=11&lang=enCrane КС–8165 with lifting capacity 100 tons was delivered to the Chernobyl NPP industrial site. It will be engaged into works on recovering the confinement of Unit 4 Turbine Hall.
This crane, along with the other two being already on the site, will be used to remove the remaining wall panels damaged as a result of the collapse in February this year. These works are of high complexity, because a direct access to the panels is blocked by metal towers erected during elimination of the accident consequences in 1986. Following the removal of the damaged panels from behind the metal towers and their bringing down on the ground, they will be fragmented and transported out for disposal at the RWDF “Buryakovka”.
In addition Crane КС–8165 will be used for installation of a covering three-dimensional block, by which the opening in the roof of Unit 4 Turbine Hall at axes 50-52 will be closed. Another crane, the forth one, lifting Crane POTAIN MD-3200 will assembled on the site to lift and install the covering three-dimensional block. All metal structures of the covering three-dimensional block have been already delivered to 10-km zone, and part of them has been already delivered to the ChNPP industrial site for pre-assembly
...Another 6 (six !) years ago by the Russian military invasion plan was developed in Ukraine. In the invasion plan envisaged, in order to intimidate and demoralize the population of Ukraine, apply air demonstration nuclear explosion over the territory Polesie. Quote from the article I.Dzhadana "Operation" Clockwork Orange '"(2008):" Air Demonstration nuclear strike in the stratosphere in the southern part of the Pripyat marshes produced at night, would help immensely in this case. He would not inflict significant damage, except for disabling power lines and electrical appliances in a radius of 100 km. But he would have been seen in hating "Muscovites" Lviv and even in Poland. He immediately sobered be hotheads, clearly indicating answered by a serious commitment to the Kremlin. "
For skeptics who believe that this revision chornobyl.in.ua exalted Bandera eating breakfast Russian children and the elderly, we note that in the article "Operation Clockwork Orange" (again, written by Russian military analyst!) Described three stages of intervention in Ukraine. Surprisingly, the first phase of the war with Ukraine, described in the article has already been implemented. Seizure of the Crimea occurred in full compliance with the script operations "Clockwork Orange." Similarities are impressive - the author with an accuracy not only have the number of Russian invaders, the script of their movement in the Crimea, but even just have numbers of military units of the Russian Federation armed forces involved in the conflict. And this, in April 2008! In this regard, there is currently no reason to distrust the Russian analyst (more about the stages of Russian intervention on the territory of Ukrainehttp://www.russ.ru/pole/Operaciya-Mehanicheskij-apel-sin
LabratSR said:
April 17, 2014
Within the NSC project on the construction site were performed the following work:
- Delivery of equipment to the site and basic designs western arches;
- Erection western arches;
- Installation of suspension towers for crane girders of the main cranes;
- Preparation and installation of containers piddomkrachuvannya western arches;
- Pre-assembly of panels cladding;
- Installation runs for housing;
- Installation of external and internal cladding (West Arch);
- Installation of air ducts bulk of zahыdnoyi of the arches of stainless steel;
- Placing the foundation service area (southern grillage reinforcing tape);
- Placement of root piles for the foundation of the service area (south strip);
- Placing her building technology and supporting facilities.
Erection western arches to the first head:
According to the project (including the weight of the secondary structures and crane girders) - 4513.0 tons
Assembled - 4166.06 tons (92.31%)
Erection of the eastern part of the Arch:
According to the project (including the weight of the secondary structures, crane girders and bolts) - 13,743.109 tons
Assembled - 12,791.71 tons (93.08%)
Covering the bases service areas:
Concrete for the project - 11795.73 m 3, signed 5674.2 m 3 (48.10%)
Fittings for the project - 2447.009 tons produced 1598.649 tons (65.33%)
Arrangement of root piles (south strip):
The project - 216 units, completed by the project marks 152 units (70.37%)
http://www.chnpp.gov.ua/index.php?option=com_content&view=article&id=1449&lang=en
The Cabinet of Ministers of Ukraine in the current year on direct activities on decommissioning Chernobyl and transformation of the "Shelter" into an ecologically safe system 745 271 000 UAH.
This is stated in the government decree number 108 of April 16, 2014.
According to the document, to maintain in a safe condition of the first, second, third Chernobyl NPP and existing spent fuel storage will be allocated Rs 376.508 million for decommissioning and partial dismantling of individual systems and components units - UAH 63.617 million.
To carry out organizational and technical measures for the management, operation, maintenance, repair systems, life support Chernobyl ensure monitoring of the Nuclear and Radiation Safety Cabinet send UAH 234.182 million.
The creation of the industrial area of Chernobyl infrastructure for the management of spent nuclear fuel and radioactive waste in 2014 provided 27,264,000 USD, and for the release of nuclear fuel units - 43.7 million UAH.
As UNIAN reported earlier, the Cabinet of Ministers of Ukraine in 2013 sent for events on decommissioning Chernobyl and the transformation of the "Shelter" into an ecologically safe system of 728.271 million UAH.
Completion of construction of the "Shelter" at Unit 4 of the Chernobyl nuclear power plant is scheduled for 2015. The cost of construction is estimated at 980 million euros, while contracts with concern "Novarka" fixed sum of 935 million euros.