How much work does a crane and gravity do on a large box?

Click For Summary
SUMMARY

The discussion centers on the work done by a crane and the force of gravity on a box being lifted. It is established that the crane does an amount of work equal to mgh, while gravity does -mgh. The tension in the string must exceed the gravitational force momentarily to initiate movement, but once the box is in motion, the tension can equal the gravitational force. The net work done on the box is related to its change in kinetic energy, not solely the work done by the crane.

PREREQUISITES
  • Understanding of basic physics concepts such as work, energy, and forces.
  • Familiarity with the equations E(p) = mgh and W = Fs.
  • Knowledge of Newton's laws of motion, particularly regarding forces and acceleration.
  • Concept of net work and its relation to kinetic energy.
NEXT STEPS
  • Study the relationship between work and kinetic energy in physics.
  • Learn about the implications of constant velocity versus acceleration in lifting scenarios.
  • Explore the design considerations of crane booms, including material and structural integrity.
  • Investigate the principles of tension in strings and cables under varying loads.
USEFUL FOR

Students of physics, engineering professionals, and anyone interested in understanding the mechanics of lifting forces and work done in physical systems.

Warlic
Messages
32
Reaction score
0

Homework Statement


upload_2015-11-30_11-38-45.png
[/B]

Homework Equations


E(p)=mgh
W = Fs

3. The Attempt at a Solution

The book says the crane does mgh amount of work, while gravity does -mgh.
What I don't understand is, for the box to be lifted up, doesn't string tension force have to be bigger than gravity - or else it would remain in place and not accelerate upwards? If so, formula for work is W=Fs, the distance s is same for both forces, but string tension force is bigger, so doesn't crane do more absolute work on the box that gravity?
 
Physics news on Phys.org
Warlic said:

Homework Statement


View attachment 92644[/B]

Homework Equations


E(p)=mgh
W = Fs

3. The Attempt at a Solution

The book says the crane does mgh amount of work, while gravity does -mgh.
What I don't understand is, for the box to be lifted up, doesn't string tension force have to be bigger than gravity - or else it would remain in place and not accelerate upwards? If so, formula for work is W=Fs, the distance s is same for both forces, but string tension force is bigger, so doesn't crane do more absolute work on the box that gravity?
Who says that the box is accelerating upwards? You can lift things perfectly well at constant velocity.

You're making the mistake by assuming that if acceleration = 0, then velocity = 0. If something has zero acceleration, it could be stationary or moving at constant velocity. You can't tell which situation applies unless you are given more information. In this case, the crane is 'slowly lifting' the box, which implies that velocity is not zero.
 
  • Like
Likes   Reactions: Warlic
SteamKing said:
Who says that the box is accelerating upwards? You can lift things perfectly well at constant velocity.

You're making the mistake by assuming that if acceleration = 0, then velocity = 0. If something has zero acceleration, it could be stationary or moving at constant velocity. You can't tell which situation applies unless you are given more information. In this case, the crane is 'slowly lifting' the box, which implies that velocity is not zero.
Thank you, now I feel stupid.
 
Warlic said:
Thank you, now I feel stupid.
You shouldn't. You are quite right that the tension had to exceed mg at some point, but perhaps only by the tiniest amount, and for the briefest period. Once the box is in motion, the tension can drop back to equal mgh until the box is at the desired height. It might just take a while.

By the way, as I understand it, the book should not insist the crane did mgh of work on the box. It did mgh of work, but the net work done on an object is its increase in KE. If you throw a ball up with enough speed to reach height h then you do mgh work on the ball, then the ball does that same work against gravity (i.e. it does that work on the ball-Earth system). But if the crane lifts the mass slowly and steadily to a height h, you could equally say the crane did mgh work against gravity and none on the box.
 
  • Like
Likes   Reactions: nrqed and Warlic
Why crane booms are made up of rectangular cross sections instead of circular section?
 
Manimech said:
Why crane booms are made up of rectangular cross sections instead of circular section?
Probably because they are easier to make.
If you wish to pursue this question, please create a new thread, not in a homework forum.
 

Similar threads

  • · Replies 12 ·
Replies
12
Views
10K
  • · Replies 14 ·
Replies
14
Views
8K
  • · Replies 17 ·
Replies
17
Views
4K
Replies
4
Views
2K
  • · Replies 4 ·
Replies
4
Views
1K
  • · Replies 14 ·
Replies
14
Views
3K
  • · Replies 1 ·
Replies
1
Views
4K
  • · Replies 11 ·
Replies
11
Views
3K
  • · Replies 7 ·
Replies
7
Views
3K
  • · Replies 8 ·
Replies
8
Views
2K