Reactive Power: Consumption, Production and Instantaneous Power

Click For Summary

Discussion Overview

The discussion revolves around the concepts of reactive power, its consumption and production, and the relationship between instantaneous power and complex power. Participants explore theoretical and practical aspects of these concepts within the context of electrical engineering and power systems.

Discussion Character

  • Debate/contested
  • Technical explanation
  • Conceptual clarification

Main Points Raised

  • Some participants assert that reactive power is "borrowed" rather than consumed, suggesting that it is returned to the system.
  • There is a claim that power stations do not produce reactive power but rather supply it, with some arguing that this is a matter of terminology.
  • One participant explains that in steady-state AC analysis, complex power is represented as S = V * I*, where P is active power and Q is reactive power.
  • Another participant discusses the relationship between instantaneous power and complex power, stating that they are not directly related.
  • There are differing views on how reactive power affects the ability of power stations to deliver real power, with some suggesting that providing reactive power limits real power delivery.
  • Participants discuss the control of reactive power production in power stations through methods like over/under-magnetizing generators.
  • One participant introduces the concept of the grid as an "infinite bus," indicating that generators must adjust the phase of the current to maintain grid stability.

Areas of Agreement / Disagreement

Participants express multiple competing views regarding the terminology and concepts surrounding reactive power. There is no consensus on whether reactive power is consumed or supplied, and the relationship between instantaneous and complex power remains debated.

Contextual Notes

Some participants highlight the complexity of the topic and the importance of precise terminology, while others suggest that the discussion could be simplified. There are unresolved assumptions regarding the definitions of reactive power and its implications in practical scenarios.

Who May Find This Useful

This discussion may be of interest to electrical engineers, students studying power systems, and professionals involved in energy management and grid stability.

Passionate Eng
Messages
36
Reaction score
1
Why does a load consume reactive power?
How can we produce reactive power?
And what is the relationship between instantaneous power and complex power?
 
Engineering news on Phys.org
  • You do not consume reactive power, you "borrow" it and then "pay it back".
  • You do not produce reactive power. You supply power, the load may be more or less reactive.
Passionate Eng said:
And what is the relationship between instantaneous power and complex power?
That depends very much on the application. I have seen examples (CRT scanning) where the peak voltage and the peak current were both quite high - but never simultaneously.
 
Last edited:
Svein said:
  • You do not consume reactive power, you "borrow" it and then "pays it back".
  • You do not produce reactive power. You supply power, the load may be more or less reactive.
In the framework of steady-state AC analysis, the OP's lingo is correct.

Passionate Eng said:
Why does a load consume reactive power?
Assuming use of the passive sign convention, the complex power is given by:
$$
\mathbf{S} = \mathbf{V}\overline{\mathbf{I}} = P + jQ
$$
where ##\mathbf{V}, \mathbf{I}## are RMS phasors for voltage and current, respectively, and ##P, Q## is the active and reactive power consumed, respectively.

##Q## will, for instance, be positive for an ideal inductor, i.e. it is said to consume reactive power.

Passionate Eng said:
How can we produce reactive power?
##Q## will, for instance, be negative for an ideal capacitor, i.e. it is said to produce reactive power.

Passionate Eng said:
And what is the relationship between instantaneous power and complex power?
There is none. Complex power is defined in terms of phasors.
 
  • Like
Likes   Reactions: Hesch
Homework questions?
 
Real power is the product of voltage and the in-phase component of the current.
The product of voltage and the quadrature-phase current is reactive circulating energy.

Since cables have real resistance, real power is needed to circulate a reactive current. That power is the product of the reactive current by the voltage drop along the wires due to the reactive current, not the voltage between the conductors as with real power.
 
Thx for all ^_^
 
Svein said:
  • You do not consume reactive power, you "borrow" it and then "pay it back".
  • You do not produce reactive power. You supply power, the load may be more or less reactive.

hmm- that's being a bit picky.

Power stations generate reactive power to balance the grid
 
  • Like
Likes   Reactions: Hesch
William White said:
Power stations generate reactive power to balance the grid
Properly speaking: They introduce a reactive load in order to "balance the grid".
 
like I said, you are being picky; everybody knows what is meant by generating reactive power.

Dont be pedantic - it does not help.

Power stations generate power. Some of it is VARS, some is VAs. The ratio can be changed by the power station manager.I understood the OPs question, and the manager of the power station would too.
 
  • #10
William White said:
everybody knows what is meant by generating reactive power.
I am a mathematician - in my world there is no such thing as "everybody knows". A power station generates voltage and supplies current to the load. The phase of the load current is determined by the load, not by the generator.
 
  • #11
Svein said:
I power station generates voltage and supplies current to the load. The phase of the load current is determined by the load, not by the generator.

The generator itself and all its associated gubbins is a load. When everyday people talk about the generator in a power station, they are talking about the plant that burns fuel and produces electricity.

- let's say it is widely known (rather than everybody knows).

yes - it is acceptable to "produce reactive power" and the manager of the power station would ask the plant technician to do so when required without any argument.
 
Last edited by a moderator:
  • #12
OK so this blew up a little - I wanted to post earlier. I disagree, they do not "generate" reactive power they provide it! Providing reactive power decreases the amount of real power they can provide (if they are maxed out) because you are "pushing" current and not delivering anything. Conversely - and on the face counter-intuitively, - you DO CONSUME reactive power - because the system providing the POWER has to supply enough POWER to deliver the current (in and then out). If your house is a pure inductor - the utility has to supply current, the generator has to supply that current through the system - it takes energy to supply that current.

Consider this - you buy a gold ring - the vendor has to supply it - they ship it to you, you send it back - the vendor sees"cost - but you received nothing - and they do not charge for shipping. If you did this everyday - the vendor would say they have to stop. But they are not generating a new gold ring every day.
 
  • #13
And the utility does measure it KVARH - is measuring it.
 
  • #14
Thread closed temporarily for some cleanup...

Thread re-opened.
 
  • #15
William White said:
like I said, you are being picky; everybody knows what is meant by generating reactive power.

Dont be pedantic - it does not help.

Power stations generate power. Some of it is VARS, some is VAs. The ratio can be changed by the power station manager.I understood the OPs question, and the manager of the power station would too.

I am learning from the discussion in this thread, and don't think it's a bad thing to clarify the terminology.
 
  • #16
Svein said:
The phase of the load current is determined by the load, not by the generator.
That's not right. In a grid ( connected to several power stations ) you can control the production of reactive power in a single power station by over/under-magnetizing the generator, thereby distributing the production/consumption amongst the power stations in a way, that leads to minimum conducting power losses in power lines.
 
  • #17
Hesch said:
That's not right. In a grid ( connected to several power stations ) you can control the production of reactive power in a single power station by over/under-magnetizing the generator, thereby distributing the production/consumption amongst the power stations in a way, that leads to minimum conducting power losses in power lines.
Yes. I do not quite see how you control the current phase in that way, unless you introduce an output impedance in the generator that is (partly) reactive. What staggers me, however, is the problem of doing any control at all on a high voltage transfer line (think 700kV)...
 
  • #18
Svein said:
I do not quite see how you control the current phase in that way, unless you introduce an output impedance in the generator that is (partly) reactive.
Say you have this 700kV transfer line, and you magnetize a single connected generator to yield 800kV ( transformed ), the generator cannot change the voltage of the 700kV ( too many competiting power stations ), so the 800kV ( which is there as for the single power station ) must be vectorially folded, so that the sum of the folded vectors are kept within a radius of 700kV from 0V, and when you fold the 800kV vector, a transverse vector must be created, resulting in a reactive power.
Svein said:
What staggers me, however, is the problem of doing any control at all on a high voltage transfer line (think 700kV)...
Well, the 700kV and the power is created by power stations. They ( and the consumers ) are the ones to control it.
 
Last edited:
  • #19
You can make the concept of VAR as difficult as you like by making the situation more complex. KISS.
But once you have the concept of the grid being an “infinite bus”, with many sources and sinks, you will realize that the VAR on the grid must be satisfied by generators providing a current slightly out of phase with the local voltage.

Generators are adjusting the phase of the current they produce to satisfy the bus. On average they must balance the grid VA + VAR, or the power frequency would change.
http://www.openelectrical.org/wiki/index.php?title=Infinite_Bus
 
  • #20
Almost nothing is done about this or really anything at High Voltage - it is almost exclusively for transmission. Generation maxes out around 23KV - the scary part is that due to the current at this voltage there is no circuit breaker between the Generator and the Step UP Transformer for large generators. So all of the Generator protection has to be done at the HV side.

And the generator are NOT the only source of reactive power - they can and do add significant bulk capacitance at the distribution level, preferably before reaching the transmission level where the added reactive current decreases the capacity of the system. http://tdworld.com/blog/real-reactive-power-transfer-formulas-basics
 
Last edited by a moderator:
  • #21
Windadct said:
And the generator are NOT the only source of reactive power - they can and do add significant bulk capacitance at the distribution level, preferably before reaching the transmission level where the added reactive current decreases the capacity of the system.
Yes, or you connect a huge synchronous motor to the transmission line, doing no mechanical work, just over-magnetize it, and it will produce adjustable reactive power, because it acts as an adjustable capacitive load.
 
  • #22
Still I think the OP (PE) has an essay question for homework we are just spoon feeding.
 

Similar threads

  • · Replies 8 ·
Replies
8
Views
3K
  • · Replies 2 ·
Replies
2
Views
2K
Replies
11
Views
3K
  • · Replies 3 ·
Replies
3
Views
2K
Replies
21
Views
2K
  • · Replies 5 ·
Replies
5
Views
2K
  • · Replies 38 ·
2
Replies
38
Views
5K
  • · Replies 4 ·
Replies
4
Views
2K
  • · Replies 8 ·
Replies
8
Views
11K
Replies
4
Views
3K