Optimizing Transformer Parameters for Efficient Substation Performance | Tims

Click For Summary

Discussion Overview

The discussion revolves around estimating parameters for a new transformer intended for a substation, focusing on nominal capacity, average repair costs, unsupplied energy costs, and average repair time. The context is primarily theoretical and exploratory, aimed at gathering sensible assumptions for research purposes.

Discussion Character

  • Exploratory
  • Technical explanation
  • Homework-related

Main Points Raised

  • Tims inquires about reasonable assumptions for parameters of a $100 million transformer, including nominal capacity, average repair cost, unsupplied energy cost, and average repair time.
  • Another participant questions the validity of the $100 million figure, suggesting that $1 million (CAD) might be more realistic and asks if the proposed configuration could indeed yield a capacity of 10^5 KW.
  • One participant recommends researching typical costs for a 500/230 kV transformer and provides a link to a relevant document for further information.
  • A suggestion is made to contact a specific user known for expertise in high-power transmission and substation equipment for additional insights.

Areas of Agreement / Disagreement

Participants have not reached a consensus on the proposed parameters, and multiple competing views regarding the cost and capacity estimates remain. The discussion is ongoing and unresolved.

Contextual Notes

There are limitations regarding the assumptions made about costs and capacities, as well as the dependence on specific configurations and definitions that have not been fully explored or agreed upon.

tims.corbett
Messages
2
Reaction score
0
Hi All,

I am required to assume some parameters for my research,
For a new transformer worth $100 million for a substation, what likely could be sensible for these

parameters?

Nominal Capacity? (Example 10^5 KW)
Average Repair Cost? ($1 million ?)
Unsupplied energy cost? ($3 kWh ?)
Average Repair time? (1 year?)

Thanks,
Tims
 
Engineering news on Phys.org
tims.corbett said:
Hi All,

I am required to assume some parameters for my research,
For a new transformer worth $100 million for a substation, what likely could be sensible for these

parameters?

Nominal Capacity? (Example 10^5 KW)
Average Repair Cost? ($1 million ?)
Unsupplied energy cost? ($3 kWh ?)
Average Repair time? (1 year?)

Thanks,
Tims

What other sources of information are you looking into to find this?
 

Similar threads

Replies
35
Views
8K
  • · Replies 21 ·
Replies
21
Views
10K
  • · Replies 2 ·
Replies
2
Views
1K
  • · Replies 7 ·
Replies
7
Views
4K
  • · Replies 8 ·
Replies
8
Views
3K
  • · Replies 21 ·
Replies
21
Views
3K
  • · Replies 8 ·
Replies
8
Views
2K
  • · Replies 2 ·
Replies
2
Views
4K
Replies
2
Views
7K
  • · Replies 7 ·
Replies
7
Views
4K