What is the Work Required to Stretch a Spring?

Click For Summary

Homework Help Overview

The problem involves calculating the work required to stretch a spring with a given spring constant from its equilibrium position. The original poster states the spring is initially stretched 0.21 m and seeks to find the work needed to stretch it an additional 0.14 m.

Discussion Character

  • Mathematical reasoning, Problem interpretation, Assumption checking

Approaches and Questions Raised

  • Participants discuss the formula for work done on a spring and question the correctness of the calculations provided. There is confusion regarding whether the work should be negative and the interpretation of the distance values used in the calculations.

Discussion Status

Some participants have attempted calculations and shared their results, while others have pointed out potential errors in the approach. There is an ongoing exploration of the correct interpretation of the problem and the calculations involved, with no explicit consensus reached.

Contextual Notes

There is a noted typo in the distance value used in the calculations, leading to further questioning about the correct values to apply. Participants are also considering the implications of the work being negative and the area under the force-distance curve.

blayman5
Messages
43
Reaction score
0

Homework Statement


A spring with spring constant of 29 N/m is
stretched 0.21mfromits equilibrium position.
How much work must be done to stretch it
an additional 0.14 m? Answer in units of J.


Homework Equations


W=-kx(x)/2


The Attempt at a Solution


I solved it and got 0.4263 and it was wrong. does it need to be negative?
 
Physics news on Phys.org
blayman5 said:

Homework Statement


A spring with spring constant of 29 N/m is
stretched 0.21mfromits equilibrium position.
How much work must be done to stretch it
an additional 0.14 m? Answer in units of J.


Homework Equations


W=-kx(x)/2


The Attempt at a Solution


I solved it and got 0.4263 and it was wrong. does it need to be negative?

How did you arrive at that number?
 
i did ((29)(0.21)(0.14))/2 =0.4263. does it need to be negative?
 
blayman5 said:
i did ((29)(0.21)(0.14))/2 =0.4263. does it need to be negative?

That's not quite right.

Additional work = Difference in work = 29*(.21+14)2/2 - 29*(.21)2/2
 
Ok so that means it would equal
29*(.21+14)2/2 - 29*(.21)2/2 =1.1368

Thanks
 
blayman5 said:
Ok so that means it would equal
29*(.21+14)2/2 - 29*(.21)2/2 =1.1368

Thanks

That's what I got anyway. What you need to remember is that work is the area under the force and distance curve over the range of the curve.

Cheers
 
i will remember thanks
 
LowlyPion said:
That's not quite right.

Additional work = Difference in work = 29*(.21+14)2/2 - 29*(.21)2/2

wait...

wait wait... why is it 14 instead of .14?
 
dleccord said:
wait...

wait wait... why is it 14 instead of .14?

He got the right answer and the 14 was apparently a typo. Calculate it out and you will see the inner sum needs to sum to .35.
 

Similar threads

Replies
20
Views
3K
Replies
6
Views
1K
  • · Replies 5 ·
Replies
5
Views
1K
Replies
17
Views
2K
  • · Replies 58 ·
2
Replies
58
Views
3K
  • · Replies 17 ·
Replies
17
Views
3K
  • · Replies 12 ·
Replies
12
Views
2K
  • · Replies 2 ·
Replies
2
Views
2K
Replies
14
Views
3K
  • · Replies 14 ·
Replies
14
Views
4K