The 9th mid & long term meeting was held on 27 August 2012:
http://www.meti.go.jp/earthquake/nuclear/20120827_01.html
1) Previous related topics:
The 8th meeting (30 July 2012)
https://www.physicsforums.com/showpost.php?p=4020743&postcount=13588
The 7th meeting (25 June 2012)
https://www.physicsforums.com/showpost.php?p=3979794&postcount=13512
The 6th meeting (25 May 2012) :
https://www.physicsforums.com/showpost.php?p=3933442&postcount=13399
The 5th meeting (23 April 2012) :
https://www.physicsforums.com/showpost.php?p=3881074&postcount=12979
The 4th meeting (28 March 2012) :
https://www.physicsforums.com/showpost.php?p=3838108&postcount=12764
The 3rd meeting (27 February 2012) was translated into English on Tepco's website :
http://www.tepco.co.jp/en/nu/fukushima-np/roadmap/conference-e.html
2) Translation:
27 August 2012 government-Tokyo Electric mid and long term response committee, steering committee (9th meeting)
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01a.pdf Agenda
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01b.pdf Participants
Document 1
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01c.pdf Abstract of the proceedings of 8th steering committee meeting
Document 2: Plant status
Document 2-1: Plant status
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01d.pdf Plant parameters
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01e.pdf Accumulated water storage status
Document 3 Study and execution of each special plan
3-1 Cooling by closed loop water injection
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01f.pdf Schedule
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01g.pdf Inspection inside unit 1's PCV
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01h.pdf Installation of unit 2 PCV atmosphere thermometer
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01j.pdf Nitrogen injection into unit 1's suppression chamber
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01k.pdf Status of pipe water removal method study, toward the installation of unit 2 RPV alternative thermometer
3-2 Treatment of accumulated water
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01m.pdf Schedule
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01n.pdf Status of ground water bypass study
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01p.pdf Simulation of quantities generated by accumulated water treatment, and installation of additional storage tanks
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01q.pdf Additional tank installation plan
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01r.pdf Multinuclide removal facility (ALPS) qualification test status
3-3 Countermeasures to reduce environmental radiations
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01s.pdf Schedule
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01t.pdf Consequences on water quality of the covering of the sea floor in the harbour
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01u.pdf Results of evaluation of additional releases from reactor buildings
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01v.pdf Unification of methods to evaluate radiation doses at site boundaries
3-4 Improvement of working conditions
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01w.pdf Schedule
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01x.pdf Countermeasures to fulfill radiation management at Fukushima Daiichi nuclear power plant
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01y.pdf Guidelines in response to the APD dosimeter problem and execution schedule
3-5 Countermeasures for spent fuels pools
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01z.pdf Schedule
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01aa.pdf Debris removal work, reactor building top part, unit 3
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01bb.pdf Debris removal work, reactor building top part, unit 4
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01cc.pdf Unit 1 operating floor status survey results
3-6 Preparations for fuel debris removal
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01dd.pdf Schedule
3-7 Treatment and disposal of radioactive waste
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01ee.pdf Schedule
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01ff.pdf Debris, cut down trees management status
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01gg.pdf Cut down trees (branches, leaves, roots) temperature monitoring status
Document 4
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01hh.pdf Evaluation in response to the radiation management report dealing with Alarm Pocket Dosimeter (APD) misuse
Document 5
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_01jj.pdf roadmap progress (abstract)
27 August 2012 government-Tokyo Electric mid and long term response committee, technical development progress headquarters (8th meeting) (
http://www.meti.go.jp/earthquake/nuclear/20120827_02.html )
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_02a.pdf Agenda
Document 1
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_02b.pdf Research and development plans toward the decommissioning of Tokyo Electric Fukushima Daiichi units 1~4 (abstract)
Document 2
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_02c.pdf Progress status of development of machinery and equipments to prepare fuel debris removal
Document 3
http://www.meti.go.jp/earthquake/nuclear/pdf/120827/120827_02d.pdf Fukushima workshop on development of machinery and equipments toward the decommissioning of Tokyo Electric Fukushima Daiichi nuclear power plant (abstract of results)