Hello,
Just looking into some clarrification. If a customer states that they want the following system, what is it they mean (note, it is 3-phase 4W 120/208V:
1200 A MAIN DISTRIBUTION
C/W:
1- 600 A house panel feed
2 - 100 A tenant sections
2 - 200 A tenant sections
Basically the 1200 A is split up into a 600 A fusible switch, two 200 A fusible switches, and two 100 A fusible switches?
Furthermore, I was told that fusible switches had to be used as opposed to circuit breakers. Can anyone describe why?
Just looking into some clarrification. If a customer states that they want the following system, what is it they mean (note, it is 3-phase 4W 120/208V:
1200 A MAIN DISTRIBUTION
C/W:
1- 600 A house panel feed
2 - 100 A tenant sections
2 - 200 A tenant sections
Basically the 1200 A is split up into a 600 A fusible switch, two 200 A fusible switches, and two 100 A fusible switches?
Furthermore, I was told that fusible switches had to be used as opposed to circuit breakers. Can anyone describe why?