Solve Inverse Proportion Road Works in 14 Days

  • Thread starter Thread starter LiHJ
  • Start date Start date
  • Tags Tags
    Inverse
AI Thread Summary
The problem involves calculating the total time needed to complete road repairs with varying numbers of workers. Initially, 4 workers are on the job for 14 days, completing 56 worker days of labor. After 14 days, 10 additional workers join, bringing the total to 14 workers. The remaining work requires 112 worker days, which can be completed in 8 days by the 14 workers. Thus, the total time to finish the road works is 22 days.
LiHJ
Messages
43
Reaction score
2

Homework Statement


Dear Mentors and PF helpers,

Please help me with this question as my junior asked me but I have some doubts in it:

It takes 4 workers to complete repairing the road in 42 days. Suppose that 14 days into the road works, 10 more workers are brought into help out in the road works. Calculate the total number of days needed to complete the road works in this case.

Homework Equations



y = k/x , where k is a constant and y and x are variables [/B]

The Attempt at a Solution


let y be days and x be number of workers
42 = k / 4
168 = k

From the question they trying to ask if during the 14 days of work with 14 men but after this 14 days it's going to be 4 men working again.

Suppose there are 14 workers ("10 more workers are brought into help..."):

d = 168 / 14 = 12

It takes 12 days to complete the repairing, but why the question says " Suppose that 14 days into the road works ..."

Can anyone help me? Thank you for your time.
 
Physics news on Phys.org
LiHJ said:
From the question they trying to ask if during the 14 days of work with 14 men but after this 14 days it's going to be 4 men working again.

No. I think there are 14 days of work by 4 men. Then 14 men work to finish the road.First find the rate R at which 1 worker works. Use the fact that 4 men working at that rate can finish 1 road in 42 days.

(4 workers) (R) (42 days ) = 1 road

Solve for R

Then write the equation that says 14 men working at rate R for X days build 1-(4)(R)(14) of the road.
 
LiHJ said:

Homework Statement


Dear Mentors and PF helpers,

Please help me with this question as my junior asked me but I have some doubts in it:

It takes 4 workers to complete repairing the road in 42 days. Suppose that 14 days into the road works, 10 more workers are brought into help out in the road works. Calculate the total number of days needed to complete the road works in this case.

Homework Equations



y = k/x , where k is a constant and y and x are variables [/B]

The Attempt at a Solution


let y be days and x be number of workers
42 = k / 4
168 = k
And what does k represent?
LiHJ said:
From the question they trying to ask if during the 14 days of work with 14 men but after this 14 days it's going to be 4 men working again.

Suppose there are 14 workers ("10 more workers are brought into help..."):

d = 168 / 14 = 12

It takes 12 days to complete the repairing, but why the question says " Suppose that 14 days into the road works ..."

Can anyone help me? Thank you for your time.
Your approach needs to be more systematic, taking into account that for the first 14 days only 4 men are working on the road, and then after that, an additional 10 men are working on it. What fraction of the job can the first four men do in the first 14 days? From this, what fraction of the job can each man do per day, assuming that all four men work at the same rate? How much of the job is left after the first 14 days? How long will it take for all of the men (all 14 of them) to finish the job?
 
Thank you Stephen and Mr Mark.

Here's my working:

If the job is to be done by 1 day, it will need 42 x 4 = 168 workers.
So first is being done by 4 men in 14 days, so is like 56 workers already did their part.
Left over work is 168 - 56 = 112 workers still needed to complete it.
Number of days left = 112/ 14 = 8 days
So total number of days required = 14+8 = 22 days
 
I agree, except that I would change the words slightly. The unit of labor is "worker days" (similar to the idea of "man hours").

If 1 road is built by 4 men in 42 days, it will need 42 x 4 = 168 worker days.
The first phase is being done by 4 men in 14 days, they accomplish 56 worker days..
Left over work is 168 - 56 = 112 worker days still needed to complete it.
Number of days left to finish the job = 112/ 14 = 8 days
So total number of days required = 14+8 = 22 days
 
I tried to combine those 2 formulas but it didn't work. I tried using another case where there are 2 red balls and 2 blue balls only so when combining the formula I got ##\frac{(4-1)!}{2!2!}=\frac{3}{2}## which does not make sense. Is there any formula to calculate cyclic permutation of identical objects or I have to do it by listing all the possibilities? Thanks
Since ##px^9+q## is the factor, then ##x^9=\frac{-q}{p}## will be one of the roots. Let ##f(x)=27x^{18}+bx^9+70##, then: $$27\left(\frac{-q}{p}\right)^2+b\left(\frac{-q}{p}\right)+70=0$$ $$b=27 \frac{q}{p}+70 \frac{p}{q}$$ $$b=\frac{27q^2+70p^2}{pq}$$ From this expression, it looks like there is no greatest value of ##b## because increasing the value of ##p## and ##q## will also increase the value of ##b##. How to find the greatest value of ##b##? Thanks
Back
Top