Man-Days and Man-Hours: Understanding Units of Work Measurement

Click For Summary
SUMMARY

The discussion centers on the calculation of work measurement units, specifically man-days and man-hours. It presents a problem where three men complete a job in 12 days, with two men being three times as fast as the third. The correct solution indicates that one of the faster men would take 28 days to complete the job alone. Additionally, the concept of man-day is clarified as the amount of work one man can accomplish in a single day, contrasting with man-hours, which can represent various combinations of manpower and time.

PREREQUISITES
  • Understanding of basic algebraic equations
  • Familiarity with work-rate problems
  • Knowledge of units of measurement in project management
  • Concept of man-hours and man-days in work estimation
NEXT STEPS
  • Research "work-rate problems in algebra" for further practice
  • Explore "project management estimation techniques" for effective planning
  • Learn about "man-hours vs. man-days" in project reporting
  • Study "resource allocation strategies" to optimize workforce efficiency
USEFUL FOR

Project managers, engineers, and anyone involved in work estimation and resource allocation will benefit from this discussion.

paulmdrdo1
Messages
382
Reaction score
0
If 3 m e n do a job in 12 days and two of the me n are three time s as fast as the third,
how long will it take one of the faster men to do the job ?

this is how I solved it

let x = required time for one of the faster men to do the job alone
3x = time taken by third to finish a job alone.

$\frac{1}{3x}+\frac{1}{3x}+\frac{1}{x}=\frac{1}{12}$

x = 20 days

is this correct?
 
Mathematics news on Phys.org
No, that's not correct. The way I see it, if would take the slow man $12\cdot7=84$ days to complete the job alone, so one of the faster men would take $$\frac{84}{3}=28$$ days.

You would find this also by using:

$$\frac{1}{3x}+\frac{2}{x}=\frac{1}{12}$$

$$\frac{7}{3x}=\frac{1}{12}$$

$$\frac{3x}{7}=12$$

$$x=28$$
 
$12\cdot7=84$ where did you get this?
 
The two faster men can do the work of 6 slower men, so having the two faster men and one slow man working is equivalent to 7 slow men working.
 
markFL, I saw a solution to this that uses "man-day" which until now I don't have a complete understanding. can you explain about it?

some say that man-day is the work-rate of a single man in one day
some say that it is the amount of work a single person need to complete a job.
some say it is a work-load. which confuses me all the time I encounter these types of problems.

I'm hoping that you could show me the explanation about it. Thanks!
 
Simply put, a man-day is the amount of work one man can get done in one day.

You may have heard a more commonly used unit of man-hours. For example, it may be reported to have taken 2,000 man-hours to complete the design of the PCM for the latest hypercar. This may mean 1 man working for 2,000 hours or 2,000 men working for 1 hour, or 4 men working an average of 500 hours each, etc.
 

Similar threads

  • · Replies 1 ·
Replies
1
Views
5K
  • · Replies 8 ·
Replies
8
Views
2K
  • · Replies 1 ·
Replies
1
Views
2K
  • · Replies 1 ·
Replies
1
Views
3K
  • · Replies 6 ·
Replies
6
Views
3K
  • · Replies 36 ·
2
Replies
36
Views
8K
  • · Replies 14 ·
Replies
14
Views
2K
  • · Replies 1 ·
Replies
1
Views
2K
  • · Replies 8 ·
Replies
8
Views
2K
  • · Replies 6 ·
Replies
6
Views
2K