Solving a Probability Problem in Construction Planning

  • Thread starter Thread starter tomtk
  • Start date Start date
  • Tags Tags
    Probability
AI Thread Summary
The discussion revolves around a probability problem in construction planning, specifically calculating the likelihood of completing a project in 43 days given a mean duration of 50 days and a variance of 3.06. The initial attempt at solving the problem incorrectly calculated the z-score, leading to confusion about the probability of completion within the desired timeframe. Clarification was provided that the z-score should be calculated correctly to determine the corresponding probability from the standard normal distribution. The significance level of 5% indeed corresponds to a 95% confidence interval, but the focus should remain on finding the correct z-value to assess the project's completion probability. Accurate interpretation of the z-score and its relationship to the normal distribution is essential for solving this probability question effectively.
tomtk
Messages
1
Reaction score
0
Hi from Melbourne.

I have a rudimentary probability question that you will probably find amusing but hopefully you can also help me!

I am studying construction planning and this question is taken from an old exam paper.

Homework Statement



"Risk analysis: At 5% level of significance, what is the probability of completing the project at or earlier than the employer's desired duration in the question above.

The question above requires that project is completed 7 days earlier than the normal duration, μ

Where:
Mean, μ = 50
Required duration, D = 43
Variance, σ² = 3.06
Standad deviation, σ = 1.749

Homework Equations



I assume Z = D - μ / √σ²

The Attempt at a Solution



I thought the answer would be z=43-50/√3.06
This gives 4.001, would this mean there is a less than 1% probability of the project being completed in 43 days?

On further reading I also discovered that a 5% level of significance is the same as a 95% confidence interval? If this is the case, doesn't this make the z value 1.645? In which case none of the variables for the equation are unknown.

As you can see I have got myself very confused :

Any and all help will be greatly appreciated. I'll have this forum open all day (and night)!
 
Physics news on Phys.org
tomtk said:
Hi from Melbourne.

I have a rudimentary probability question that you will probably find amusing but hopefully you can also help me!

I am studying construction planning and this question is taken from an old exam paper.

Homework Statement



"Risk analysis: At 5% level of significance, what is the probability of completing the project at or earlier than the employer's desired duration in the question above.

The question above requires that project is completed 7 days earlier than the normal duration, μ

Where:
Mean, μ = 50
Required duration, D = 43
Variance, σ² = 3.06
Standad deviation, σ = 1.749

Homework Equations



I assume Z = D - μ / √σ²
You need parentheses here.

z = (x - μ )/ σ

tomtk said:

The Attempt at a Solution



I thought the answer would be z=43-50/√3.06
You need parentheses here, too, otherwise this will be interpreted as 43 - (50/√3.06
).

The answer to the question is not a value of z - it's the probability of completing the project at or earlier than the employer's desired duration (43 days).
tomtk said:
This gives 4.001, would this mean there is a less than 1% probability of the project being completed in 43 days?
Wouldn't this give you a z value of -4.001? Where are you getting a probability of 1%?
tomtk said:
On further reading I also discovered that a 5% level of significance is the same as a 95% confidence interval?
Yes.
tomtk said:
If this is the case, doesn't this make the z value 1.645? In which case none of the variables for the equation are unknown.
The mean length of jobs is 50 days, with a standard deviation of 3.06 days. What fraction of jobs are done in 43 days or fewer? To answer this question look at the standard normal distribution to see how much area under the curve corresponds to your (corrected) z value.
 
I picked up this problem from the Schaum's series book titled "College Mathematics" by Ayres/Schmidt. It is a solved problem in the book. But what surprised me was that the solution to this problem was given in one line without any explanation. I could, therefore, not understand how the given one-line solution was reached. The one-line solution in the book says: The equation is ##x \cos{\omega} +y \sin{\omega} - 5 = 0##, ##\omega## being the parameter. From my side, the only thing I could...
Essentially I just have this problem that I'm stuck on, on a sheet about complex numbers: Show that, for ##|r|<1,## $$1+r\cos(x)+r^2\cos(2x)+r^3\cos(3x)...=\frac{1-r\cos(x)}{1-2r\cos(x)+r^2}$$ My first thought was to express it as a geometric series, where the real part of the sum of the series would be the series you see above: $$1+re^{ix}+r^2e^{2ix}+r^3e^{3ix}...$$ The sum of this series is just: $$\frac{(re^{ix})^n-1}{re^{ix} - 1}$$ I'm having some trouble trying to figure out what to...

Similar threads

Back
Top