I am not sure where this goes , if this is the wrong place sorry.
The question is asking for
Time required to build the part.
The 4 is the total length of the part.
It also says the scanning speed is 80ft/min
the spot size is 0.010 in
delay time is 7 sec/layer
The formula that is given
Ti=(Ai/(vD))+Td
Where
Ti= time to complete layer
Ai=area of the layer
v= average scanning speed of the laser beam at the surface
D= diameter of the spot size
Td= delay time between layers to re position the worktable
I want to know the steps of this forumla.
The question is asking for
Time required to build the part.
The 4 is the total length of the part.
It also says the scanning speed is 80ft/min
the spot size is 0.010 in
delay time is 7 sec/layer
The formula that is given
Ti=(Ai/(vD))+Td
Where
Ti= time to complete layer
Ai=area of the layer
v= average scanning speed of the laser beam at the surface
D= diameter of the spot size
Td= delay time between layers to re position the worktable
I want to know the steps of this forumla.