Designing a partially submerged foundation requires careful consideration of buoyancy and soil conditions. The structure's dimensions and concrete volume suggest it may float if not properly anchored, as the displaced water volume exceeds the concrete's weight. Solutions discussed include increasing wall thickness, using anchors or bracing, and potentially driving piles into the ground for stability. Active drainage around the foundation could also mitigate buoyancy effects. Consulting with a civil engineer is recommended to assess soil and rock types for effective design.
Dhillon123
Messages
1
Reaction score
0
I am looking for some insight with a problem I have. I am trying to design a foundation that is partially under the current water table.

It is a hollow rectangle that is 30 m long, 11 m wide and 9 m high with a wall thickness of 0.5 m, it is attached to a triangular shape foundation that is 35 m long, 11 m wide and 9 m high with a wall thickness of 0.5 m. The structure sticks out 0.5 m above the current ground level.

I was able to calculate the volume of the concrete structure which is 890.27 m^3
Using the water table information we found that the volume of water displaced is 4076.325 m^3

From this I know I need to calculate the buoyancy force and try to get neutral buoyancy so it does not move. I am just wondering how to go about this. Should we increase the dimensions of the structure (thickness is the only thing that we can think or altering) or consider using anchors or bracing to equal out the forces.
 
Engineering news on Phys.org
I guess you want to avoid having a concrete boat type of situation.
Density of heavy concrete is around 2500 kg/cubic meter, and that of water 1000 kg/ cubic meter.

From what you have stated about the volumes, it looks like your boat would float!

Depending upon soil conditions, anchoring, and all that, a consultation with cival engineer may be the best route to pursue.
Someone other here at PF though may have experience and knowledge to help you out.
 
You must consider the buoyancy in the soil rather than in pure water. Soil has greater density so the hydrostatic pressure at depth is often sufficient to force water above the surface.

Maybe you could actively drain the area immediately outside the wall so as to reduce the soil movement and buoyancy effect.

Another solution might be to drive piles deep into the ground, they can then anchor the structure.

What is the soil type and depths?
What is the rock type and depth?
 
Thread 'Where is my curb stop?'
My water meter is submerged under water for about 95% of the year. Today I took a photograph of the inside of my water meter box because today is one of the rare days that my water meter is not submerged in water. Here is the photograph that I took of my water meter with the cover on: Here is a photograph I took of my water meter with the cover off: I edited the photograph to draw a red circle around a knob on my water meter. Is that knob that I drew a red circle around my meter...
Hi all, i have some questions about the tesla turbine: is a tesla turbine more efficient than a steam engine or a stirling engine ? about the discs of the tesla turbine warping because of the high speed rotations; does running the engine on a lower speed solve that or will the discs warp anyway after time ? what is the difference in efficiency between the tesla turbine running at high speed and running it at a lower speed ( as fast as possible but low enough to not warp de discs) and: i...
Back
Top