The contractors may submit high tender in lumpsum contract

  • Context: Engineering 
  • Thread starter Thread starter shivajikobardan
  • Start date Start date
Click For Summary

Discussion Overview

The discussion revolves around the implications of contractors submitting high tenders in lump sum contracts, exploring the reasons behind this practice and the understanding of its meaning within the context of construction contracts.

Discussion Character

  • Conceptual clarification, Debate/contested

Main Points Raised

  • One participant expresses confusion about the meaning of contractors submitting high tenders in lump sum contracts, questioning whether the contract is finalized once the money is given.
  • Another participant explains that contractors may ask for more than the actual cost to account for uncertainties and avoid potential losses, suggesting that a buffer is included in their tender.
  • Some participants mention "unforeseen conditions" and "errors and omissions" in construction documents as reasons for contractors to submit higher tenders.
  • A later reply challenges the relevance of unforeseen conditions and errors to the concept of high tenders, stating that these factors do not directly relate to the submission of a high tender.

Areas of Agreement / Disagreement

Participants do not reach a consensus on the implications of high tenders, with some agreeing on the rationale behind including buffers for uncertainties, while others dispute the relevance of specific reasons cited.

Contextual Notes

The discussion highlights potential misunderstandings regarding the relationship between high tenders and unforeseen conditions, indicating that assumptions about the contract's finality and cost implications may vary among participants.

shivajikobardan
Messages
637
Reaction score
54
Homework Statement
what does it mean really?
Relevant Equations
none.
I don't understand what does this mean?

What does this mean? Please guide. I don't understand. In lump sum contract, once the contractor gives money it is all done isn't it. What does contractors submit high tender.
1645784294233.png
 
Physics news on Phys.org
It means the contractors may ask for more than it will actually cost.

Think about a lumpsum contract from the side of the contractor. You try and estimate as best as you can what to will cost, but you have to prepare for uncertainties and don't want to end up losing money because the job actually costed more than planned. The contractors will thus tend to include a buffer for uncertainties in their tender.
 
  • Like
Likes   Reactions: shivajikobardan and Lnewqban
“Unforeseen conditions” is one reason.
“Errors and omissions” in the construction documents and specifications is another reason.
 
DrClaude said:
It means the contractors may ask for more than it will actually cost.

Think about a lumpsum contract from the side of the contractor. You try and estimate as best as you can what to will cost, but you have to prepare for uncertainties and don't want to end up losing money because the job actually costed more than planned. The contractors will thus tend to include a buffer for uncertainties in their tender.
makes sense. thank you.
 
Lnewqban said:
“Unforeseen conditions” is one reason.
“Errors and omissions” in the construction documents and specifications is another reason.
Those are nothing to do with "the contractors may submit [a] high tender"; exposure to additional cost due to claims or variations are not addressed by that slide.
 

Similar threads

Replies
2
Views
2K
  • · Replies 8 ·
Replies
8
Views
2K
  • · Replies 3 ·
Replies
3
Views
2K
  • · Replies 4 ·
Replies
4
Views
1K
  • · Replies 6 ·
Replies
6
Views
2K
  • · Replies 19 ·
Replies
19
Views
5K
Replies
3
Views
2K
  • · Replies 3 ·
Replies
3
Views
1K
  • · Replies 7 ·
Replies
7
Views
3K
  • · Replies 33 ·
2
Replies
33
Views
5K