Backyard class 2 pole zip lines

  • Thread starter Thread starter Goodluck
  • Start date Start date
  • Tags Tags
    Class Lines Pole
AI Thread Summary
The discussion focuses on constructing a backyard zip line with specific dimensions and materials, including Class 2 telephone poles and galvanized cable. Key concerns include determining the appropriate tension for the zip line and guy wires under various conditions, particularly with a 250-pound rider. Safety is emphasized, highlighting the importance of proper installation and the potential dangers associated with incorrect tension and support systems. The conversation also touches on the engineering aspects of guy wire angles and anchor strength, stressing the need for careful planning and execution. Overall, the thread underscores the complexity and safety considerations involved in building a zip line.
Goodluck
Messages
2
Reaction score
0
Looking to build a zip line with 4% decline for the kids with:

Class 2 50' CCA syp Class II telephone poles sunk 6.5ft.
3/8" cable 7x19 Galzanized cable for guy wire and zip line.

1st zip: 100ft Starting at 26ft on a 6' hill->Ending at 22ft
2nd zip: 120ft Starting at 22ft -> Ending at 17.2 on a 6'hill
3rd zip:100ft Starting at 17.2ft on a 6' hill -> Ending 19.2ft
4th zip:150ft Starting at 19.2 -> Ending 13.2ft

8ft. Ground anchors on Guy wire tension pull tested to 5000lbs. preferably at 45degrees to pole within 1 foot of zip line attachment location.

I plan on buying a tension meter to check cable tension.
A few questions:

What should the Zip Line Tension be with 250lb person from center of zip line
What should the guy wire tension be without 250lbs person on zip line?
What should the guy wire tension be with 250lb person on zip line?
Up to what angle am I ok installing the guy anchors to? 45 is recommended. but we may be short on space.

Looking at the guy wires from a site plan view; What angles should I set the guy wires in relation to the zip lines? On the same plane for the second pole and third pole as the incoming zip lines? and on the 1st, 3rd and last poles at what degree?

See attached files for more info that I have gathered and sketched up. I would like to learn as much as possible in this process. I am somewhat comfortable with math, but it has been a few years.
 

Attachments

  • zip-line-thoughts-1.jpg
    zip-line-thoughts-1.jpg
    64.1 KB · Views: 1,201
  • zip-line-thoughts-2.jpg
    zip-line-thoughts-2.jpg
    46.9 KB · Views: 1,770
  • zip-line-thoughts-3.jpg
    zip-line-thoughts-3.jpg
    42.6 KB · Views: 1,251
  • zip-line-thoughts-4.jpg
    zip-line-thoughts-4.jpg
    25.2 KB · Views: 973
  • zip-line-thoughts-5.jpg
    zip-line-thoughts-5.jpg
    45.8 KB · Views: 1,667
  • zip-line-thoughts-6.jpg
    zip-line-thoughts-6.jpg
    42.7 KB · Views: 1,347
Engineering news on Phys.org
Goodluck said:
Looking to build a zip line with 4% decline for the kids with:

Class 2 50' CCA syp Class II telephone poles sunk 6.5ft.
3/8" cable 7x19 Galzanized cable for guy wire and zip line.

1st zip: 100ft Starting at 26ft on a 6' hill->Ending at 22ft
2nd zip: 120ft Starting at 22ft -> Ending at 17.2 on a 6'hill
3rd zip:100ft Starting at 17.2ft on a 6' hill -> Ending 19.2ft
4th zip:150ft Starting at 19.2 -> Ending 13.2ft

8ft. Ground anchors on Guy wire tension pull tested to 5000lbs. preferably at 45degrees to pole within 1 foot of zip line attachment location.

I plan on buying a tension meter to check cable tension.
A few questions:

What should the Zip Line Tension be with 250lb person from center of zip line
What should the guy wire tension be without 250lbs person on zip line?
What should the guy wire tension be with 250lb person on zip line?
Up to what angle am I ok installing the guy anchors to? 45 is recommended. but we may be short on space.

Looking at the guy wires from a site plan view; What angles should I set the guy wires in relation to the zip lines? On the same plane for the second pole and third pole as the incoming zip lines? and on the 1st, 3rd and last poles at what degree?

See attached files for more info that I have gathered and sketched up. I would like to learn as much as possible in this process. I am somewhat comfortable with math, but it has been a few years.
As I am sure you know, zip lines can be extremely dangerous if not properly installed for proper sags and tensions , hardware connections, support systems, etc. I would carefully follow installation instructions provided by a reputable zip line dealer. And properly guying the poles , setting the poles, installing the anchors, etc. , is an art in itself. I wouldn't fool with it myself. And that second pole is a tough one... You essentially double the loads on the guying and poles by reversing cable direction. And steeper guys lead to greater guy tensions and pulls on anchors, and if too steep , become ineffective in preventing pole leans. Sorry I can't be more helpful, but this is serious stuff requiring engineering and construction expertise.
 
Thank you for your input, there will only be one rider at a time.
 
Last edited:
Goodluck said:
Thank you for your input, there will only be one rider at a time.
Yes, but the wire had to be pulled up rather tight for the zip to work properly, perhaps on the order of 1 percent sag which in a 100 ft span yields about 300 pounds tension under the wires self weight. Now add a person and the tension might be say 2000 pounds. With a 1 to 1 guy slope , say 3000 pounds in the guys, you have two, so not too bad , but throw in a safety factor of 4 and you have an ult load per guy of 6000 pounds. Steep the slope to 1 on 2 and you've got 9000 pounds in the guy and anchor. Now this is all doable, but what is the holding strength of the anchors? Soil conditions? Anchor type? Compacted backfill? Hardware connections? You've got to be sure there is no slippage, no anchor creep out, no bending in anchor , etc. actually tour guy arrangement looks pretty good, I'd separate the anchors at the double guys about 10 ft min. These are just rough numbers and not for design.
 
Goodluck: First, (1) what is "a conventional top-rope belay system"? (2) What is "a conventional traversing element operated using a self-belayed lanyard system"? (3) Which of these two systems are you using? (4) What does "static belay" mean? (5) What does "dynamic belay" mean?
 
Goodluck: Please cancel my questions in post 5. I now figured out items 4 and 5. And, I currently think you will be using item 2 in post 5, not item 1.
 
Hi all, I have a question. So from the derivation of the Isentropic process relationship PV^gamma = constant, there is a step dW = PdV, which can only be said for quasi-equilibrium (or reversible) processes. As such I believe PV^gamma = constant (and the family of equations) should not be applicable to just adiabatic processes? Ie, it should be applicable only for adiabatic + reversible = isentropic processes? However, I've seen couple of online notes/books, and...
Thread 'How can I find the cleanout for my building drain?'
I am a long distance truck driver, but I recently completed a plumbing program with Stratford Career Institute. In the chapter of my textbook Repairing DWV Systems, the author says that if there is a clog in the building drain, one can clear out the clog by using a snake augur or maybe some other type of tool into the cleanout for the building drain. The author said that the cleanout for the building drain is usually near the stack. I live in a duplex townhouse. Just out of curiosity, I...

Similar threads

Replies
1
Views
7K
Replies
1
Views
5K
Replies
3
Views
21K
Replies
108
Views
18K
Replies
12
Views
10K
Replies
54
Views
7K