Economics: IRR vs NPV - Comparing Projects A and C

  • Thread starter Thread starter martine
  • Start date Start date
  • Tags Tags
    Economics
AI Thread Summary
The discussion centers on comparing two investment projects, A and C, using IRR and NPV metrics. Project A has a higher IRR of 13% and a lower NPV of 18, while Project C has a lower IRR of 10% but a higher NPV of 23. Despite Project C's better NPV, Project A is considered preferable, potentially due to quicker payback of the initial investment. The complexities of IRR, particularly its limitations in comparing projects with different cash flow timings, are highlighted. Ultimately, the choice between projects should consider both IRR and NPV, along with the timing of cash flows.
martine
Messages
27
Reaction score
1
Hello,

I've had an intro economics course recently and there are still a couple of questions unanswered.

One of the examples given where a handfull of projects with an initial investment and positive cash flows the following years. The question was which project is preferable when looking at IRR, NPV and a couple of other tools.

It was decided that the first two methods where most important and that project A and C looked most promising. Both had the same initial investment.
A: high first cashflow, moderate cashflow for a few years, then none anymore
C: low but stable cashflow throughout into the future

A: IRR ~13% NPV ~18
C: IRR ~10% NPV ~23

I only wrote down a few advantages and disadvantages for both methods and the remark that project A is preferable to C. The question is why? The IRR I learned cannot be used for ranking across projects and the NPV is lower. Maybe because the initial investment is paid back quicker or are there other arguments for that? I know I should have asked the lecturer, but he was speeding so quickly through his slides that I just tried to keep up with taking notes and id not really think about what he was saying.

Thanks a lot for any hints.
M.
 
Physics news on Phys.org
Many will say that this is because IRR assumes reinvestment at the IRR rate, but it is not quite correct. However, for projects with large early cashflows it will be overstated relative to NPV. The basic idea is that one would rather have an investment that compounded at 15% for ten years than one that returned 20% in one year and then would have to be re-invested.
 
This page has a good explanation:
http://hspm.sph.sc.edu/COURSES/ECON/Invest/invest.html

In essence, the IRR reports the discount rate at which the NPV would be zero, but it's hard to compare investments on the basis of IRR only if the relative timings of payments differ significantly, because the NPV zero point may not tell much about the value at other discount rates.
 
Last edited by a moderator:
martine said:
Hello,

I've had an intro economics course recently and there are still a couple of questions unanswered.

One of the examples given where a handfull of projects with an initial investment and positive cash flows the following years. The question was which project is preferable when looking at IRR, NPV and a couple of other tools.

It was decided that the first two methods where most important and that project A and C looked most promising. Both had the same initial investment.
A: high first cashflow, moderate cashflow for a few years, then none anymore
C: low but stable cashflow throughout into the future

A: IRR ~13% NPV ~18
C: IRR ~10% NPV ~23

I only wrote down a few advantages and disadvantages for both methods and the remark that project A is preferable to C. The question is why? The IRR I learned cannot be used for ranking across projects and the NPV is lower. Maybe because the initial investment is paid back quicker or are there other arguments for that? I know I should have asked the lecturer, but he was speeding so quickly through his slides that I just tried to keep up with taking notes and id not really think about what he was saying.

Thanks a lot for any hints.
M.

If by IRR you mean Incremental Rate of Return and not Internal Rate of Return, then you'll select the project that has an IRR greater than your MARR. When comparing projects one typically uses Incremental Analysis to determine which one maximizes the NPW of the alternatives.

CS
 
Just ONCE, I wanted to see a post titled Status Update that was not a blatant, annoying spam post by a new member. So here it is. Today was a good day here in Northern Wisconsin. Fall colors are here, no mosquitos, no deer flies, and mild temperature, so my morning run was unusually nice. Only two meetings today, and both went well. The deer that was road killed just down the road two weeks ago is now fully decomposed, so no more smell. Somebody has a spike buck skull for their...
Thread 'RIP George F. Smoot III (1945-2025)'
https://en.wikipedia.org/wiki/George_Smoot https://physics.berkeley.edu/people/faculty/george-smoot-iii https://apc.u-paris.fr/fr/memory-george-fitzgerald-smoot-iii https://elements.lbl.gov/news/honoring-the-legacy-of-george-smoot/ https://www.nobelprize.org/prizes/physics/2006/smoot/facts/ https://www.aps.org/publications/apsnews/200611/nobel.cfm https://inspirehep.net/authors/988263 Structure in the COBE Differential Microwave Radiometer First-Year Maps (Astrophysical Journal...

Similar threads

Back
Top