Hiddencamper
- 403
- 182
Red_Blue said:These are quite interesting studies. The Japanese Fukushima reports also mention two papers on hydrogen explosions outside of primary containment, which they consider obscure (one modelling Olkiluoto NPP in Finland and the other Browns Ferry NPP). It appears a lot of theoretical work on severe accident mitigation was simply overlooked or at least not integrated to EOPs. Some of that was even Japanese experiences, such as using plant fire department fire engines for core injection, provisions which had been prepared after earthquake damage to other plants, but formal procedures apparently had not been updated to Fukushima EOP.
A completely another question is that even if there had been much more extensive formal severe accident mitigation guidance available, would they have really implemented it? One of the main human factors issues identified by the Japanese reports, especially the Cabinet ones, is the comparison of how F-2 managed the crisis by always being one step ahead of things. They always had a Plan A in action, while preparing for Plan B to be implemented immediately should there be indication of Plan A failure. And when they were switching Plan A, they tested the viability of implementation of the entire new plan several times before actually carrying the switch over.
In contrast in F-1 this was never achieved when it became obvious that RHR and other sea water reliant systems were going to be out of operation for days. After that, there was over reliance on Plan A continuing to work despite lack of monitoring data and Plan B formulation only started when information came in putting Plan A viability in doubt, sometimes only after several misunderstandings and delays in information flow.
If we accept for Unit 1 that IC in the heavily degraded condition with the internal isolation valves partially closed would not have delayed core uncovery sufficiently for work to fully restore it, even if all PCV external valves had been opened for both trains, and that there was insufficient 125VDC power to start HPCI, then it appears the logical course of action would have been to implement the fire cistern->fire engine->FP system->core spray and car batteries to the MRC for SRV remote manual depressurisation plan ASAP. The question if enough time was available for this would have to look at how long implementing the individual parts of this work took at later stages of the crisis, but with the same resources available.
It appears the biggest problems and longest delays in the accident response all came after the hydrogen explosions and when radiological conditions had degraded both inside key buildings and outside in close vicinity. Another system that took very long time to get to work was SC venting arrangements, which at the end still was only partially successful for Units 1 and 3, being unsuccessful for Unit 2 despite almost a day of trying. In F-2 it was undestood early that any work inside the RBs, including manual valve actuations should be done proactively with anticipated not forced need. They also lined up venting paths, without the need to ever use them. The same was also understood in F-1, but apparently only after observing how things had already gone sour in Unit 1.
Venting however should not have been needed for Unit 1 until many hours or couple days, had core cooling being restored before severe damage, considering how long the other units went with RCIC.
Japan's BWR EOPs were not well updated. My understanding is they were still using rev 1 or 2 (all other plants are on 3 or 4). They had to get dresden's EOPs and SAMGs to use.
They did violate EOPs in that they did not perform a blowdown at unit 1 when required. This resulted in a hot debris ejection which may have contributed to containment leakage. The only way to minimize the damage in this event was exactly as you said, which is also what EOPs say, to blowdown when level was below the fuel and flood vessel or dry well with fire pumps through the core spray header.
With no functioning level indication, and elevated containment temperature causing reference leg boiling, the operators had no indications to go off of. They didn't have enough to demonstrate that reference leg boiling was occurring, could not transition to the flooding EOP, and suffered core damage.
I probably should make another post about BWR EOPs in detail. In all cases they should have blown down the reactor if they didn't know where level was and transitioned to flooding. But they didn't have enough to know if they didn't know where level was. Pretty screwed up.