Span distance 150x50 steel tubing

  • Thread starter Thread starter DANger-is
  • Start date Start date
  • Tags Tags
    Span Steel
AI Thread Summary
The discussion centers on the feasibility of spanning 8 meters with 150 x 50 x 3mm steel tubing for a patio without a midspan post. It is noted that without a central post, the steel tube would be overstressed, necessitating additional support. The maximum allowable span between posts is calculated to be approximately 5.14 meters, assuming a tensile yield strength of 275 MPa and a patio height of no more than 1200 mm. Concerns are raised about the attachment of purlins to the steel tubing and the potential for lateral movement. Overall, proper structural support and adherence to building codes are emphasized for safety and stability.
DANger-is
Messages
2
Reaction score
0
I'm designing a patio which is connected to a house on one side, 8m x 2.4m

150 x 50 x 3mm steel tubing around the outside with 140 x 50 hardwood purlins, spaced at 1m intervals (2.4m long each).

I would like to span the 8m with only posts on the ends. Is this possible or will there be to much sag?

Thanks
Dan
 
Engineering news on Phys.org
DANger-is: With no midspan post, your given 8 m steel tube would be overstressed. Therefore, a post at the midspan of your given 8 m steel tube is also needed.
 
Isn't there standards for this? You can't lookup the building codes?
 
Thanks for getting back to me nvn. I'm trying to span as fare as possible withou having a support in the middle. Given that the beam can overhang the posts, I would think I could span the rhs 6.5 m between supports. Which would result in approximately 600 mm overhang on both ends. Any thoughts?
 
DANger-is: What is the material specification, and tensile yield strength (Sty), of your RHS? Assuming Sty = 275 MPa, then the maximum allowable span length between your two posts would be L1 = 5140 mm, using your current steel tube cross section size and wall thickness. This assumes your patio is no more than ~1200 mm above the ground. If the patio elevation exceeds roughly 1200 mm, then the allowable span length L1 would be less.

Are your "purlins" (joists) actually attached to your RHS? And is the midspan of your first RHS attached to the house? Or can your joists slip longitudinally (horizontally), such that your outer RHS has no midspan lateral (horizontal) support near its compression flange?
 
Last edited:
Hi all, I have a question. So from the derivation of the Isentropic process relationship PV^gamma = constant, there is a step dW = PdV, which can only be said for quasi-equilibrium (or reversible) processes. As such I believe PV^gamma = constant (and the family of equations) should not be applicable to just adiabatic processes? Ie, it should be applicable only for adiabatic + reversible = isentropic processes? However, I've seen couple of online notes/books, and...
Thread 'How can I find the cleanout for my building drain?'
I am a long distance truck driver, but I recently completed a plumbing program with Stratford Career Institute. In the chapter of my textbook Repairing DWV Systems, the author says that if there is a clog in the building drain, one can clear out the clog by using a snake augur or maybe some other type of tool into the cleanout for the building drain. The author said that the cleanout for the building drain is usually near the stack. I live in a duplex townhouse. Just out of curiosity, I...
Back
Top