Here is the last monthly mid & long term report from Tepco, dated 7 March 2013 (246 pages, 11.9MB, Japanese) :
http://www.tepco.co.jp/nu/fukushima-np/roadmap/images/d130307_01-j.pdf
I indicate the page numbers and translate the titles of each presentation. For clarity's sake, I kept the main titles "2.1" through "3.7" that used to be mentioned on the Ministry of Economy, Trade and Industry's mid and long term documents.
2-1: Plant status
16/246 - 19/246 : Plant parameters
20/246 - 21/246 : Accumulated water storage status
3-1 Cooling by closed loop water injection
22/246 - 23/246 : Closed loop water injection cooling schedule
24/246 - 27/246 : Schedule revision of installation work of a nuclear reactor water injection system using the condensate storage tank as source
28/246 - 36/246 : Reliability improvement work on units 1,2,3 reactor injection points (feedwater systems)
37/246 - 46/246 : Results of TIP guide tube soundness verifications for the purpose of unit 2 reactor internal inspection and thermometer installation
47/246 - 57/246 : Execution of monitoring instruments installation and internal investigation into unit 2 PCV
A result report dated 19 March 2013 is available in English : http://www.tepco.co.jp/en/nu/fukushima-np/handouts/2013/images/handouts_130319_03-e.pdf indicating some problems : "Since the CRD replacement rail could not be found, the investigation of the rail and the area near the pedestal could not be performed. The camera was able to reach the upper part of the grating on the first floor". Also the guide pipe "got stuck".
3-2 Treatment of accumulated water
58/246 : Accumulated water treatment schedule
59/246 - 74/246 : Groundwater bypass progress status and preparations for starting
75/246 - 145/246 : Status of the safety assessment studies needed for the start of the multinuclide removal facility
3-3 Countermeasures to reduce environmental radiations
146/246 - 148/246 : Results of evaluation of additional releases from reactor buildings
3-4 Improvement of working conditions
149/246 - 150/246 : Improvement of working conditions schedule
3-5 Countermeasures for spent fuels pools
151/246 - 152/246 : Spent fuel pool countermeasure schedule
153/246 : working area layout map of units 3 and 4 top part debris removal work and covering work for the purpose of fuel removal
154/246 : Debris removal work, reactor building top part, unit 3
155/246 : Debris removal work, reactor building top part, unit 4
156/246 - 159/246 : Unit 2 reactor building operating floor gamma camera inspection results (prompt report)
An English language result report, dated 22 February 2013, is available :
http://www.tepco.co.jp/en/nu/fukushima-np/handouts/2013/images/handouts_130222_04-e.pdf
160/246 : Investigation Results of Unit 3 Spent Fuel Pool using Underwater Camera (Performed on February 14, 15, 16 and 18)
An English version, dated 21 february 2013, is available here : http://www.tepco.co.jp/en/nu/fukushima-np/handouts/2013/images/handouts_130221_01-e.pdf
161/246 - 166/246 : Revision of the schedule of unit 3 reactor building top part debris removal work
167/246 - 174/246 : Completion of the removal of steel truss debris above Unit 3 SFP
A few pages have been translated into English at http://www.tepco.co.jp/en/nu/fukushima-np/handouts/2013/images/handouts_130206_01-e.pdf (dated 6 February 2013)
3-6 Preparations for fuel debris removal
175/246 - 176/246 : fuel debris removal preparation work schedule
177/246 - 193/246 : Analysis results of reactor building contamination samples, as part of the "development of indoors remote decontamination technology" project
194/246 - 207/246 : Reopening of inspection into unit 2 vent pipe lower part surroundings
Related English language documents :
http://www.tepco.co.jp/en/nu/fukushima-np/handouts/2013/images/handouts_130315_01-e.pdf (March 15)
http://www.tepco.co.jp/en/nu/fukushima-np/handouts/2013/images/handouts_130314_01-e.pdf (March 14)
http://www.tepco.co.jp/en/nu/fukushima-np/handouts/2013/images/handouts_130313_03-e.pdf (March 13)
http://www.tepco.co.jp/en/nu/fukushima-np/handouts/2013/images/handouts_130306_03-e.pdf (March 6)
http://www.tepco.co.jp/en/nu/fukushima-np/handouts/2013/images/handouts_130305_01-e.pdf (March 5)
208/246 - 218/246 : Removal of obstacles such as the debris on units 1 and 3 first floors
219/246 - 228/246 : Unit 1 torus room inspection results
Related English language document : http://www.tepco.co.jp/en/nu/fukushima-np/handouts/2013/images/handouts_130222_05-e.pdf (22 February 2013)
3-7 Treatment and disposal of radioactive waste
229/246 : treatment and disposal of radioactive waste (schedule)
230/246 : Debris, cut down trees management status (as of 31 January 2013)
231/246 - 234/246 : Debris, cut down trees radiation reduction countermeasures progress status
235/246 - 246/246 : Radiation analysis of sampled debris and cut down trees (interim report) (by JAEA)