AntonL
- 521
- 0
michael200 said:Let's please stop this discussion about "double layers" of fuel in the SFP. The depth of the fuel pool is about 40 ft and the height of a fuel assembly in the SFP racks is about 14 ft. Plant technical specifications require a minimum water level of about 20 ft above irradiated fuel in the SFP. This technical specification requirement could never be met if two fuel assembilies were stacked on top of each other. The very idea of such a thing would be impractical.
When a utility increases the capacity of the SFP, they do it by replacing the exisiting used fuel storage racks in the SFP with racks that allow the fuel to be placed closer together (higher density). The geometry is analyzed and possible change to the neutron absorber panels in the fuel racks are changed to preclude criticality of the assemblies in the SFP.
Back to loss of inventory in the U4 SFP: AntonL's boiloff calculations look pretty good. There probably was also several feet (maybe 3-4 ft total) of SFP inventory loss due to pool sloshing during the earthquake. However, the inventory boiloff plus the inventory loss from sloshing wouldn't explain uncovery of the irradiated fuel in the U4 SFP. It is possible that the earthquake caused a leak in the spent fuel pool (perhaps in the gate plugs that are removed when performing refueling operations between the reactor and the SFP). Such a leak, if large, would explain the additional inventory loss. However, the limited photos of the damage to the U4 reactor indicate that there was a VERY hot fire with explosions in the lower levels of the U4 reactor building. How H2 generation and ignition at the elevation of the U4 refuel floor caused this lower building destruction is beyond me.
Ok, michael200, I take your point on doubling up so let's forget it. Thanks for sort of agreeing with my boiloff calculation and let's asume there was no leak in pool otherwise Tepco could not have waited until the 20th to replenish water, because should there have been a significant leak fuel exposure would have resulted before then.
But where does the Hydrogen come from for the explosion, forum members here agree that the explosion centre was lower down in the building on the north side, which does make sense because of the observed damage.
For that scenario I can also give a very imaginative explanation. When unit 3 was vented, could unit 4 have pumped hydrogen steam into unit 3. Unit 3 and 4 share a common exhaust stack and there was no power for fans to work to aid the exhaust procedure, Furthemore, we do not know if there are any dampers in the system and if installed I would imagine they fail open when power is lost.
Lets assume unit 3 pumped unit 4 full of steam and hydrogen, this would then be into the suppression chamber, then H2 will leak into the primary containment chamber, it would not immediately escape to the roof, as there is a seal between the reactor vessel and PCV so that PCV is not flooded during fuel transfer. The Hydrogen could have leaked out through the access hatch which would not have been sealed due to the maintenance taking place, This access hatch is on the ground floor, which is the right level for a lower explosion centre. The only question why the long delay between units 3 and 4 exploding.
@TCups have you considered that the access hatch could also have leaked at unit 3, this could explain a second and third explosion. Explosion 1 roof area, due to shock wave and vibration of the building the access hatch leaks and PCV burps through access hatch, now more hydrogen in lower building resulting in explosion 2, same happens again explosion 3 and PCV has lost a lot of pressure and the process stops, looking at the devastation on lower northern side this could work, also watch the video to the north a low level dust cloud expands further and faster than to the south
Last edited: